5400 W JEFFERSON BLVD 90016

Certificate Information: 5400 W JEFFERSON BLVD 90016

Application / Permit
22016-30000-05809
Plan Check / Job No.
B22WL00756
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
Remodel tp (E) WAREHOUSE/OFFICE BLDG TO INCLUDE: (N) ACCESSIBLE ENTRY W/ ADA LIFT ; (N) NON-RATED PARTITION IN (E) WAREHOUSE SPACE; (N) Fire RATED OPENING IN (E) WALL; REMODEL OF (E) KITCHEN. relocate 4-parking stalls to include 1-accessible parking (parking count doesn't change)
Permit Issued
Issued on 11/30/2022
Issuing Office
Metro
Current Status
Permit Finaled on 5/23/2023

Permit Application Status History

Submitted 2/28/2022 APPLICANT
Assigned to Plan Check Engineer 3/10/2022 TARIK SAOUD
Corrections Issued 3/15/2022 TARIK SAOUD
Quality Review Completed 3/22/2022 CHIHARU SUZUKI
Disabled Access Plans Picked Up 4/29/2022 APPLICANT
Applicant returned to address corrections 7/6/2022 TARIK SAOUD
Building Plans Picked Up 7/7/2022 APPLICANT
Plan Check Approved 8/1/2022 TARIK SAOUD
Issued 11/30/2022 APPLICANT
Permit Finaled 5/17/2023 JEROME BLACKWOOD

Permit Application Clearance Information

Metro Rail approval Cleared 5/10/2022 TARIK SAOUD
Community Plan Implem. Overlay Cleared 5/11/2022 KYLE WINSTON
ZI Cleared 5/11/2022 KYLE WINSTON
DAS Clearance Cleared 6/8/2022 ELIZABETH TOMS

Contact Information

Contractor Magnum Builders Inc; Lic. No.: 713775-B 25419 NARBONNE AVENUE      LOMITA, CA 907172125
Engineer Black,, Ian Robert; Lic. No.: S5505 19401 OLANA LN      HUNTINGTON BEACH, CA 92646

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 2/7/2023 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 2/8/2023 Approved DARRYL ARNOLD
Insulation 2/8/2023 Approved DARRYL ARNOLD
Footing/Foundation/Slab 2/13/2023 Partial Approval ALFREDO LOPEZ
Drywall Nailing 2/15/2023 Approved DARRYL ARNOLD
Footing/Foundation/Slab 2/16/2023 Corrections Issued ALFREDO LOPEZ
Wood Frame 2/28/2023 Partial Approval MARTIN TAVITIAN
Footing/Foundation/Slab 3/6/2023 Partial Approval JULIAN CAPUCETTI
Wood Frame 3/17/2023 Approved DARRYL ARNOLD
Drywall Nailing 4/3/2023 Partial Approval JEROME BLACKWOOD
Final 5/17/2023 Permit Finaled JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 5/17/2023 SGSOV Approved JEROME BLACKWOOD
Smoke Detectors 5/17/2023 Approved JEROME BLACKWOOD