3533 S BARRINGTON AVE 90066

Certificate Information: 3533 S BARRINGTON AVE 90066

Application / Permit
22016-30000-05119
Plan Check / Job No.
B22WL00713
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADU conversion and addition to (e) garage per CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d),(g) *** 2 of 2 ***
Permit Issued
Issued on 8/16/2022
Issuing Office
Metro
Current Status
CofO Issued on 3/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/23/2022 APPLICANT
Assigned to Plan Check Engineer 3/3/2022 FELIPE HERNANDEZ
Corrections Issued 3/24/2022 FELIPE HERNANDEZ
Quality Review Completed 3/29/2022 CHIHARU SUZUKI
Building Plans Picked Up 8/15/2022 APPLICANT
Plan Check Approved 8/16/2022 FELIPE HERNANDEZ
Issued 8/16/2022 APPLICANT
CofO in Progress 3/6/2025 DANIEL VERA
CofO Issued 3/15/2025 RICHARD STEINBACH
Permit Finaled 3/15/2025 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 4/27/2022 EDUARDO HERMOSO
Address approval Cleared 5/18/2022 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 5/23/2022 ANTHONY MAINEZ
Sewer availability Cleared 5/23/2022 ANTHONY MAINEZ
Construction near power lines Cleared 6/21/2022 RIDWAN HARDY
Grading Pre-Inspection Cleared 8/12/2022 FELIPE HERNANDEZ
Roof/Waste drainage to street Cleared 8/12/2022 DENNIS BRAGIN

Contact Information

Contractor Global Building Corporation; Lic. No.: 969892-B 17815 VENTURA BLVD   SUITE 215    ENCINO, CA 91316
Engineer Khazra,, Afshin; Lic. No.: C50250 22855 PAUL REVERE DR      CALABASAS, CA 91302
Engineer Sarrami,, Gholamali F; Lic. No.: C43720 4942 HIGHLAND VIEW AVENUE      LOS ANGELES, CA 90041

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/28/2023 Partial Approval JESUS PINEDA
Footing/Foundation/Slab 7/28/2023 Partial Approval JESUS PINEDA
PLUMBING-Rough 7/28/2023 Partial Approval JESUS PINEDA
Excavation/Setback/Form/Re-Bar 8/16/2023 Approved JESUS PINEDA
Footing/Foundation/Slab 8/16/2023 Approved JESUS PINEDA
Underground Mechanical 9/21/2023 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 10/4/2023 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 11/2/2023 Partial Inspection JESUS PINEDA
Interior/Exterior Lathing 3/18/2024 Partial Approval JESUS PINEDA
ELECTRICAL-Rough 3/22/2024 Not Ready for Inspection HERBERT GIRON
HVAC-Rough 3/22/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 4/1/2024 Corrections Issued KENNETH NAGLE
HVAC-Rough 4/1/2024 Approved KENNETH NAGLE
PLUMBING-Rough 4/1/2024 Approved KENNETH NAGLE
ELECTRICAL-Rough 4/3/2024 Approved BOBBY KEY
ELECTRICAL-Rough 4/15/2024 Approved JESUS PINEDA
PLUMBING-Rough 4/15/2024 Approved JESUS PINEDA
ELECTRICAL-Rough 4/16/2024 Approved JESUS PINEDA
HVAC-Rough 4/16/2024 Approved JESUS PINEDA
BUILDING-Rough-Frame 4/17/2024 Approved JESUS PINEDA
Green Building Rough 4/17/2024 Approved JESUS PINEDA
Verify Sprinkler Sign Off 4/17/2024 Approved JESUS PINEDA
Insulation 4/23/2024 Approved TEMISTOCLES CAAL
Shower Pan 4/23/2024 Not Ready for Inspection TEMISTOCLES CAAL
Drywall Nailing 4/29/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 5/20/2024 Approved JESUS PINEDA
Shower Pan 5/20/2024 Approved JESUS PINEDA
ELECTRICAL-Final 12/3/2024 Not Ready for Inspection DANIEL VERA
HVAC-Final 12/3/2024 Corrections Issued DANIEL VERA
PLUMBING-Final 12/3/2024 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Final 1/17/2025 Corrections Issued ARAM AVEDISIAN
Green Building Final 1/17/2025 Approved ARAM AVEDISIAN
HVAC-Final 1/17/2025 Approved ARAM AVEDISIAN
PLUMBING-Final 1/17/2025 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Final 1/24/2025 Approved DANIEL VERA
HVAC-Final 1/24/2025 Approved DANIEL VERA
PLUMBING-Final 1/24/2025 Not Ready for Inspection DANIEL VERA
Final 2/18/2025 Corrections Issued DANIEL VERA
PLUMBING-Final 2/18/2025 Approved DANIEL VERA
Reinforced Masonry Frame 2/18/2025 Not Ready for Inspection DANIEL VERA
SGSOV-Seismic Gas S/O Valve 2/18/2025 SGSOV Approved DANIEL VERA
Smoke Detectors 2/18/2025 Approved DANIEL VERA
Final 3/5/2025 OK to Issue CofO DANIEL VERA
Reinforced Masonry Frame 3/5/2025 Approved DANIEL VERA
Special/Order Compliance 3/5/2025 Partial Inspection WILBER ROSALES