1329 W 77TH ST 90044
Certificate Information: 1329 W 77TH ST 90044
- Application / Permit
- 22016-30000-04955
- Plan Check / Job No.
- B22WL00712
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 500 sf ADU conversion from (E) Detached Garage per GCS 65852.2(e)(1)(A) *** 1 of 2 ***
- Permit Issued
- Issued on 12/6/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2022 | EDWIN ESPIN |
| Corrections Issued | 3/11/2022 | EDWIN ESPIN |
| Applicant returned to address corrections | 7/27/2022 | EDWIN ESPIN |
| Applicant returned to address corrections | 9/2/2022 | JASON JANGADA |
| Applicant returned to address corrections | 10/5/2022 | JASON JANGADA |
| Applicant returned to address corrections | 11/4/2022 | RICHARD GARCIA |
| Applicant returned to address corrections | 11/17/2022 | EDWIN ESPIN |
| Building Plans Picked Up | 11/18/2022 | APPLICANT |
| Plan Check Approved | 11/22/2022 | JASON JANGADA |
| Issued | 12/6/2022 | APPLICANT |
| CofO in Progress | 7/31/2023 | MICHAEL LEWIS |
| Permit Finaled | 8/6/2023 | DEROLD HAUFF |
| CofO Issued | 8/6/2023 | DEROLD HAUFF |
| Permit Finaled | 8/6/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Hold | Cleared | 3/3/2022 | JASON SHEETS |
| Address approval | Cleared | 4/5/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 4/5/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/6/2022 | JEANETTE VONG |
| Construction near power lines | Cleared | 5/13/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Andrada,, Aprile; Lic. No.: C81097 | 27240 TURNBERRY LANE VALENCIA, CA 91355 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/22/2022 | Partial Inspection | LILIANA PORTILLO |
| Pre-Inspection | 2/17/2023 | Approved | JOHN KLARIN |
| Pre-Inspection | 4/27/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 5/10/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 5/30/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 5/30/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 5/30/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 6/14/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 6/14/2023 | Partial Inspection | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2023 | Approved | MICHAEL LEWIS |
| Insulation | 6/14/2023 | Partial Approval | MICHAEL LEWIS |
| Drywall Nailing | 6/21/2023 | Partial Approval | MICHAEL LEWIS |
| Insulation | 6/21/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 6/26/2023 | Approved | MICHAEL LEWIS |
| Final | 7/14/2023 | Corrections Issued | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 7/14/2023 | SGSOV Approved | MICHAEL LEWIS |
| Smoke Detectors | 7/14/2023 | Approved | MICHAEL LEWIS |
| Final | 7/27/2023 | OK to Issue CofO | MICHAEL LEWIS |