4550 1/2 W FRANKLIN AVE 90027
Certificate Information: 4550 1/2 W FRANKLIN AVE 90027
- Application / Permit
- 22016-30000-03284
- Plan Check / Job No.
- B22WL00447
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) detached garage and add 15'1" x 14'4" to front of (e) detached garage into an Accessory Dwelling Unit PER LAMC 12.22.A.33(c) and (d).
- Permit Issued
- Issued on 7/14/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/11/2022 | ALFREDO JARA |
| Corrections Issued | 2/14/2022 | ALFREDO JARA |
| Applicant returned to address corrections | 4/6/2022 | JASON JANGADA |
| Applicant returned to address corrections | 5/1/2022 | RICHARD GARCIA |
| Applicant returned to address corrections | 5/18/2022 | RICHARD GARCIA |
| Building Plans Picked Up | 5/19/2022 | APPLICANT |
| Applicant returned to address corrections | 6/16/2022 | RICHARD GARCIA |
| Plan Check Approved | 7/12/2022 | STANLEY RAAP |
| Issued | 7/14/2022 | APPLICANT |
| CofO in Progress | 5/30/2024 | ENRIQUE MIRELES |
| Permit Finaled | 6/10/2024 | DEROLD HAUFF |
| CofO Issued | 6/10/2024 | DEROLD HAUFF |
| Permit Finaled | 6/10/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/7/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 3/7/2022 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 3/7/2022 | CELINA MORENO |
| Sewer availability | Cleared | 3/7/2022 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 6/23/2022 | ALFREDO JARA |
| Specific Plan | Cleared | 7/8/2022 | VALENTINA KNOX |
| ZI | Cleared | 7/8/2022 | VALENTINA KNOX |
Contact Information
| Architect | Shaw,, Brett; Lic. No.: C15759 | 10401 VENICE BLVD #806 LOS ANGELES, CA 90064 |
| Contractor | Lanet / Shaw Architects Inc; Lic. No.: 768428-B | 10401 VENICE BLVD #806 LOS ANGELES, CA 90034 |
| Engineer | Niver,, Kenneth Earl; Lic. No.: S2554 | 10845 LINDBROOK DR STE 203 W LOS ANGELES, CA 90024 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/14/2022 | Approved | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 12/12/2022 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 12/30/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Deputy Drilled-In Anchors | 1/4/2023 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 1/9/2023 | Corrections Issued | JULIAN AMAYA |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2023 | Partial Approval | STUART CHAPMAN |
| HVAC-Rough | 3/14/2023 | Partial Approval | STUART CHAPMAN |
| Insulation | 4/5/2023 | Corrections Issued | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 4/6/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 4/6/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| Green Building Rough | 4/6/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 4/6/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 4/6/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 4/7/2023 | Partial Approval | JOSEPH MCGARRY |
| Insulation | 4/7/2023 | Partial Approval | JOSEPH MCGARRY |
| Rough-Elec/Plmb/HVAC | 4/7/2023 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 4/24/2023 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 4/24/2023 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 4/24/2023 | Approved | JOSEPH MCGARRY |
| Insulation | 4/28/2023 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 4/28/2023 | Corrections Issued | JOSEPH MCGARRY |
| Drywall Nailing | 5/4/2023 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 5/4/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 5/4/2023 | Partial Approval | LILIANA PORTILLO |
| Shower Pan | 5/4/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 5/22/2023 | Approved | JOSEPH MCGARRY |
| Sewer | 8/21/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| Pre-Inspection | 9/5/2023 | Partial Approval | JOSEPH MCGARRY |
| Sewer | 9/15/2023 | Corrections Issued | BRENDAN MORELLI |
| Sewer | 9/20/2023 | Corrections Issued | JOSEPH MCGARRY |
| Sewer | 9/25/2023 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 9/25/2023 | Approved | JOSEPH MCGARRY |
| Final | 11/28/2023 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 11/28/2023 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 11/28/2023 | SGSOV Not Ready | JOSEPH MCGARRY |
| Smoke Detectors | 11/28/2023 | Approved | JOSEPH MCGARRY |
| Final | 2/21/2024 | Corrections Issued | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 2/21/2024 | SGSOV Approved | ENRIQUE MIRELES |
| Final | 5/13/2024 | Corrections Issued | ENRIQUE MIRELES |
| Final | 5/28/2024 | OK to Issue CofO | ENRIQUE MIRELES |