3230 S PECK AVE 90731

Certificate Information: 3230 S PECK AVE 90731

Application / Permit
22016-30000-02836
Plan Check / Job No.
B22WL00374
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Exterior and interior remodel to convert portion of (E) SFD to (N) 140 sq ft master bathroom with adjacent 100 sq ft walk-in closet and change out window.
Permit Issued
Issued on 9/8/2022
Issuing Office
Metro
Current Status
Permit Finaled on 6/21/2024

Permit Application Status History

Submitted 1/31/2022 APPLICANT
Assigned to Plan Check Engineer 2/1/2022 JASON JANGADA
Corrections Issued 2/1/2022 JASON JANGADA
Applicant returned to address corrections 4/14/2022 JASON JANGADA
Applicant returned to address corrections 5/20/2022 RICHARD GARCIA
Applicant returned to address corrections 6/22/2022 JASON JANGADA
Applicant returned to address corrections 8/3/2022 JASON JANGADA
Building Plans Picked Up 8/5/2022 APPLICANT
Plan Check Approved 8/18/2022 KAVIAN REFAHI
Issued 9/8/2022 APPLICANT
Permit Finaled 6/20/2024 JAMES CHAVEZ

Permit Application Clearance Information

Coastal Zone Cleared 6/6/2022 DALIA MOKAYED

Contact Information

Architect Escala,, Roberto; Lic. No.: C33798 P O BOX 10411      MARINA DEL REY, CA 90295
Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Owner-Builder       ,

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/22/2023 Corrections Issued ANSON MAGLASANG
PLUMBING-Rough 8/29/2023 Not Ready for Inspection ANSON MAGLASANG
PLUMBING-Rough 9/1/2023 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 9/15/2023 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 9/27/2023 Approved JAMES CHAVEZ
Shower Pan 12/19/2023 Approved JAMES CHAVEZ
Interior/Exterior Lathing 1/19/2024 Partial Approval ANSON MAGLASANG
Final 6/14/2024 Corrections Issued JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 6/14/2024 SGSOV Approved JAMES CHAVEZ
Smoke Detectors 6/14/2024 Not Ready for Inspection JAMES CHAVEZ
Final 6/20/2024 Permit Finaled JAMES CHAVEZ
Smoke Detectors 6/20/2024 Approved JAMES CHAVEZ