1507 S LE GRANDE TER 90732

Certificate Information: 1507 S LE GRANDE TER 90732

Application / Permit
22016-30000-02476
Plan Check / Job No.
B22WL00305
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL (E) SFD AND PORCH ADDITION
Permit Issued
Issued on 6/16/2022
Issuing Office
Metro
Current Status
CofO Issued on 1/11/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/18/2022 APPLICANT
Assigned to Plan Check Engineer 2/22/2022 ALFREDO JARA
Corrections Issued 2/22/2022 ALFREDO JARA
Applicant returned to address corrections 4/4/2022 EDWIN ESPIN
Applicant returned to address corrections 4/22/2022 EDWIN ESPIN
Applicant returned to address corrections 5/19/2022 ALFREDO JARA
Building Plans Picked Up 5/31/2022 APPLICANT
Plan Check Approved 6/8/2022 FERNANDO FLORES
Issued 6/16/2022 APPLICANT
CofO in Progress 1/11/2024 JAMES CHAVEZ
CofO Issued 1/11/2024 ANSON MAGLASANG
Permit Finaled 1/11/2024 ANSON MAGLASANG

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/1/2022 KIRK LINKLATER

Contact Information

Contractor Mg Construction Group Inc; Lic. No.: 1031761-B 8430 SANTA MONICA BLVD #203      WEST HOLLYWOOD, CA 90069
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/2/2022 Partial Approval EUGENE CASSIDY
Deputy Wood Construction 9/23/2022 Conditional Approval ANSON MAGLASANG
BUILDING-Rough-Frame 9/29/2022 Not Ready for Inspection ANSON MAGLASANG
ELECTRICAL-Rough 9/29/2022 Not Ready for Inspection ANSON MAGLASANG
HVAC-Rough 9/29/2022 Approved ANSON MAGLASANG
PLUMBING-Rough 9/29/2022 Approved ANSON MAGLASANG
ELECTRICAL-Rough 10/6/2022 Approved ANSON MAGLASANG
Gas Test 10/6/2022 Approved ANSON MAGLASANG
Insulation 10/6/2022 Approved ANSON MAGLASANG
Interior/Exterior Lathing 10/6/2022 Partial Approval ANSON MAGLASANG
Drywall Nailing 10/18/2022 Approved ANSON MAGLASANG
Interior/Exterior Lathing 11/28/2022 Partial Approval ANSON MAGLASANG
Shower Pan 11/28/2022 Approved ANSON MAGLASANG
BUILDING-Rough-Frame 7/12/2023 Not Ready for Inspection JAMES CHAVEZ
Final 7/12/2023 Corrections Issued JAMES CHAVEZ
Footing/Foundation/Slab 7/12/2023 Approved JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 7/12/2023 SGSOV Not Ready JAMES CHAVEZ
Smoke Detectors 7/12/2023 Not Ready for Inspection JAMES CHAVEZ
BUILDING-Rough-Frame 7/19/2023 Approved JAMES CHAVEZ
Final 7/19/2023 Corrections Issued JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 7/19/2023 SGSOV Approved JAMES CHAVEZ
Smoke Detectors 7/19/2023 Corrections Issued JAMES CHAVEZ
Final 12/7/2023 OK to Issue CofO JAMES CHAVEZ
Smoke Detectors 12/7/2023 Approved JAMES CHAVEZ