5409 S 7TH AVE 90043

Certificate Information: 5409 S 7TH AVE 90043

Application / Permit
22016-30000-02215
Plan Check / Job No.
B22WL00221
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert existing attic space into a new 2nd floor bedroom/bath.
Permit Issued
Issued on 6/29/2022
Issuing Office
Current Status
Issued on 6/29/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/26/2022 APPLICANT
Assigned to Plan Check Engineer 1/27/2022 KAVIAN REFAHI
Corrections Issued 1/30/2022 KAVIAN REFAHI
Building Plans Picked Up 1/31/2022 APPLICANT
Applicant returned to address corrections 4/13/2022 JASON JANGADA
Applicant returned to address corrections 4/26/2022 ALFREDO JARA
Applicant returned to address corrections 5/10/2022 RICHARD GARCIA
Applicant returned to address corrections 5/26/2022 JASON JANGADA
Plan Check Approved 6/7/2022 RICHARD GARCIA
Issued 6/29/2022 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/9/2022 TREVOR QUAN
Sewer availability Cleared 2/9/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 3/2/2022 TREVOR QUAN
ZA Case Cleared 3/11/2022 DALIA MOKAYED

Contact Information

Contractor Owner-Builder       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 9/13/2022 Corrections Issued ANTHONY EGSON
Green Building Rough 9/13/2022 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 10/17/2022 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 10/17/2022 Corrections Issued ANTHONY EGSON
Wood Frame 10/17/2022 Corrections Issued ANTHONY EGSON
Wood Frame 10/31/2022 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 5/10/2023 Partial Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 8/7/2023 Partial Approval ANTHONY EGSON
Footing/Foundation/Slab 8/7/2023 Not Ready for Inspection ANTHONY EGSON
Footing/Foundation/Slab 8/11/2023 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 11/1/2023 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 11/3/2023 No Access for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 11/14/2023 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 11/17/2023 Partial Approval ANTHONY EGSON
HVAC-Rough 12/4/2023 Approved ANTHONY EGSON
PLUMBING-Rough 12/4/2023 Approved ANTHONY EGSON
ELECTRICAL-Rough 12/18/2023 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 1/23/2024 Corrections Issued ANTHONY EGSON
Green Building Rough 1/23/2024 Approved ANTHONY EGSON
Shower Pan 4/10/2024 Corrections Issued ANTHONY EGSON
Shower Pan 4/18/2024 Corrections Issued CRAIG DAVIS
Shower Pan 4/22/2024 Approved ANTHONY EGSON
Interior/Exterior Lathing 4/26/2024 Partial Approval ANTHONY EGSON
Interior/Exterior Lathing 4/30/2024 Approved ANTHONY EGSON
BUILDING-Rough-Frame 8/16/2024 Approved JOSE MACIAS
Final 8/16/2024 Conditional Approval JOSE MACIAS
Green Building Final 8/16/2024 Approved JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 8/16/2024 SGSOV Approved JOSE MACIAS
Smoke Detectors 8/16/2024 Approved JOSE MACIAS
Final 8/20/2024 Corrections Issued JOSE MACIAS
Final 12/6/2024 Corrections Issued BARRY HACHE