12560 W HAVELOCK AVE 90066
Certificate Information: 12560 W HAVELOCK AVE 90066
- Application / Permit
- 22016-30000-02195
- Plan Check / Job No.
- B22WL00208
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel (E) Single family dwelling. Per engineering design.
- Permit Issued
- Issued on 8/17/2022
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 2/16/2023
Permit Application Status History
| Submitted | 1/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/26/2022 | ALFREDO JARA |
| Corrections Issued | 1/26/2022 | ALFREDO JARA |
| Applicant returned to address corrections | 2/26/2022 | ALFREDO JARA |
| Plan Check Approved | 3/2/2022 | ALFREDO JARA |
| Building Plans Picked Up | 3/2/2022 | APPLICANT |
| Issued | 8/17/2022 | APPLICANT |
| Permit Finaled | 2/16/2023 | JESUS RODRIGUEZ |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Bela Development; Lic. No.: 1038287-B | 1023 1/2 ABBOT KINNEY BLVD VENICE, CA 90291 |
| Engineer | Chen,, Junfei; Lic. No.: C85841 | 726 FAMILY TREE IRVINE, CA 92618 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/29/2022 | Corrections Issued | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 9/15/2022 | Conditional Approval | HERBERT GIRON |
| PLUMBING-Rough | 9/28/2022 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 10/21/2022 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 10/21/2022 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 10/25/2022 | Partial Approval | HERBERT GIRON |
| HVAC-Rough | 10/25/2022 | Approved | HERBERT GIRON |
| Insulation | 10/25/2022 | Approved | HERBERT GIRON |
| Shower Pan | 10/25/2022 | Approved | HERBERT GIRON |
| Deputy Wood Construction | 10/31/2022 | Conditional Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 11/1/2022 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2022 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 11/1/2022 | Approved | HERBERT GIRON |
| Drywall Nailing | 11/8/2022 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 2/1/2023 | Corrections Issued | HERBERT GIRON |
| Final | 2/1/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 2/1/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 2/1/2023 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 2/1/2023 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 2/1/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 2/16/2023 | Approved | JESUS RODRIGUEZ |
| Final | 2/16/2023 | Permit Finaled | JESUS RODRIGUEZ |
| Green Building Final | 2/16/2023 | Approved | JESUS RODRIGUEZ |