7324 W 87TH PL 90045

Certificate Information: 7324 W 87TH PL 90045

Application / Permit
22016-30000-01782
Plan Check / Job No.
B22WL00172
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Exterior and interior remodel to (E) SFD. Scope of work to include bathroom remodel, kitchen remodel, and new doors and windows.
Permit Issued
Issued on 3/8/2022
Issuing Office
Current Status
Permit Finaled on 8/8/2022

Permit Application Status History

Submitted 1/20/2022 APPLICANT
Assigned to Plan Check Engineer 1/21/2022 JASON JANGADA
Corrections Issued 1/21/2022 JASON JANGADA
Applicant returned to address corrections 2/8/2022 MANUEL GARCIA
Plan Check Approved 2/24/2022 RICHARD GARCIA
Plan Check Approved 2/24/2022 KAREN WILLIAMS
Issued 3/8/2022 APPLICANT
Building Plans Picked Up 3/11/2022 APPLICANT
Permit Finaled 8/8/2022 BOBBY KEY

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/7/2022 JASON JANGADA

Contact Information

Contractor Chadwick & Doggett General Contracting Inc; Lic. No.: 756093-B 13428 MAXELLA AVENUE      MARINA DEL REY, CA 90292
Engineer Herrera,, Edgar E; Lic. No.: C67603 1929 GREENLEAF DR      WEST COVINA, CA 91792

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/5/2022 Conditional Approval RICHARD STEINBACH
Deputy Wood Construction 4/5/2022 Conditional Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 4/14/2022 Approved BOBBY KEY
Footing/Foundation/Slab 4/14/2022 Approved BOBBY KEY
HVAC-Rough 4/18/2022 Approved BOBBY KEY
ELECTRICAL-Rough 4/19/2022 Approved BOBBY KEY
PLUMBING-Rough 4/19/2022 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 4/19/2022 SGSOV Approved BOBBY KEY
Sewer 4/19/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 4/25/2022 Approved BOBBY KEY
Interior/Exterior Lathing 4/25/2022 Partial Approval BOBBY KEY
SGSOV-Seismic Gas S/O Valve 4/25/2022 SGSOV Approved BOBBY KEY
Shower Pan 4/25/2022 Approved BOBBY KEY
Insulation 4/28/2022 Approved BOBBY KEY
Drywall Nailing 5/3/2022 Approved BOBBY KEY
Final 7/19/2022 Corrections Issued JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 7/19/2022 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 7/19/2022 Approved JESUS RODRIGUEZ
Final 8/8/2022 Permit Finaled BOBBY KEY