4275 S KENYON AVE 90066
Certificate Information: 4275 S KENYON AVE 90066
- Application / Permit
- 22016-30000-01760
- Plan Check / Job No.
- B22WL00170
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert flat roof of existing carport to an uncovered roof deck and add stairs utility/laundry room at 2nd floor. COMPLY WITH DEPARTMENT ORDER effective date 11/02/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DAT.
- Permit Issued
- Issued on 4/1/2022
- Issuing Office
- Current Status
- CofO in Progress on 8/31/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/26/2022 | JASON JANGADA |
| Corrections Issued | 1/29/2022 | JASON JANGADA |
| Applicant returned to address corrections | 2/25/2022 | JASON JANGADA |
| Plan Check Approved | 3/26/2022 | JASON JANGADA |
| Building Plans Picked Up | 3/30/2022 | APPLICANT |
| Issued | 4/1/2022 | APPLICANT |
| CofO in Progress | 8/31/2023 | RYAN BARNES |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/11/2022 | STEVEN JIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/15/2022 | STEVEN JIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Niver,, Kenneth Earl; Lic. No.: S2554 | 10845 LINDBROOK DR STE 203 W LOS ANGELES, CA 90024 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/30/2022 | Partial Approval | RYAN BARNES |
| Final | 6/30/2022 | Not Ready for Inspection | RYAN BARNES |
| Footing/Foundation/Slab | 6/30/2022 | Approved | RYAN BARNES |
| Green Building Final | 6/30/2022 | Not Ready for Inspection | RYAN BARNES |
| Green Building Rough | 6/30/2022 | Approved | RYAN BARNES |
| SGSOV-Seismic Gas S/O Valve | 6/30/2022 | SGSOV Not Ready | RYAN BARNES |
| Smoke Detectors | 6/30/2022 | Not Ready for Inspection | RYAN BARNES |
| BUILDING-Rough-Frame | 9/15/2022 | Approved | RYAN BARNES |
| ELECTRICAL-Rough | 9/15/2022 | Approved | RYAN BARNES |
| Final | 9/15/2022 | Not Ready for Inspection | RYAN BARNES |
| Green Building Final | 9/15/2022 | Approved | RYAN BARNES |
| HVAC-Rough | 9/15/2022 | Approved | RYAN BARNES |
| PLUMBING-Rough | 9/15/2022 | Approved | RYAN BARNES |
| SGSOV-Seismic Gas S/O Valve | 9/15/2022 | SGSOV Not Ready | RYAN BARNES |
| Smoke Detectors | 9/15/2022 | Not Ready for Inspection | RYAN BARNES |
| Final | 9/27/2022 | Conditional Approval | RYAN BARNES |
| SGSOV-Seismic Gas S/O Valve | 9/27/2022 | SGSOV Approved | RYAN BARNES |
| Smoke Detectors | 9/27/2022 | Approved | RYAN BARNES |