4732 N PLACIDIA AVE 91602
Certificate Information: 4732 N PLACIDIA AVE 91602
- Application / Permit
- 22016-30000-00686
- Plan Check / Job No.
- B22WL00099
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior structural remodel of the kitchen, family/dining room and bathroom.
- Permit Issued
- Issued on 2/16/2023
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 9/12/2023
Permit Application Status History
| Submitted | 1/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2022 | KAVIAN REFAHI |
| Corrections Issued | 1/11/2022 | KAVIAN REFAHI |
| Plan Check Approved | 2/17/2022 | RICHARD GARCIA |
| Building Plans Picked Up | 2/24/2022 | APPLICANT |
| Issued | 2/16/2023 | APPLICANT |
| Permit Finaled | 9/11/2023 | JOHN HAYES |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Wood Construction | 4/12/2023 | Conditional Approval | MICHAEL SMITH |
| BUILDING-Rough-Frame | 4/17/2023 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 4/17/2023 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 4/17/2023 | Approved | JOHN HAYES |
| PLUMBING-Rough | 4/17/2023 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 4/25/2023 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 4/25/2023 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/1/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 5/1/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 5/1/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 5/1/2023 | Approved | JENNIFER RABUCHIN |
| Insulation | 5/2/2023 | Conditional Approval | THOMAS FINNILA |
| Drywall Nailing | 5/30/2023 | Approved | JENNIFER RABUCHIN |
| Insulation | 5/30/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 5/30/2023 | Approved | JENNIFER RABUCHIN |
| Final | 9/11/2023 | Permit Finaled | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 9/11/2023 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 9/11/2023 | Approved | JOHN HAYES |