13900-13902 W HAMLIN ST 91401
Certificate Information: 13900-13902 W HAMLIN ST 91401
- Application / Permit
- 22016-30000-00603
- Plan Check / Job No.
- B22WL00072
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert (E) attached garage and portion of (E) SFD into (N) ADU per GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 2/17/2022
- Issuing Office
- Current Status
- CofO Issued on 4/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2022 | JASON JANGADA |
| Corrections Issued | 1/15/2022 | JASON JANGADA |
| Building Plans Picked Up | 1/19/2022 | APPLICANT |
| Applicant returned to address corrections | 2/10/2022 | ALFREDO JARA |
| Plan Check Approved | 2/16/2022 | ALFREDO JARA |
| Issued | 2/17/2022 | APPLICANT |
| CofO in Progress | 2/21/2024 | RYAN SALAZAR |
| Permit Finaled | 4/3/2024 | RUBEN SALAS |
| CofO Issued | 4/3/2024 | RUBEN SALAS |
| Permit Finaled | 4/3/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/24/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 1/24/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/15/2022 | ABDULLAH SADOZAI |
Contact Information
| Architect | Khoudikian,, Kaaren G; Lic. No.: C13183 | 6906 FOOTHILL BLVD. TUJUNGA, CA 91042 |
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/5/2023 | Partial Inspection | RYAN SALAZAR |
| Footing/Foundation/Slab | 1/11/2024 | Partial Inspection | RYAN SALAZAR |
| Pre-Inspection | 1/11/2024 | Partial Inspection | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 1/19/2024 | Approved | RYAN SALAZAR |
| Footing/Foundation/Slab | 1/19/2024 | Approved | RYAN SALAZAR |
| Sewer | 1/19/2024 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 1/26/2024 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 1/26/2024 | Approved | RYAN SALAZAR |
| Green Building Rough | 1/26/2024 | Approved | RYAN SALAZAR |
| HVAC-Rough | 1/26/2024 | Approved | RYAN SALAZAR |
| Insulation | 1/26/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 1/26/2024 | Approved | RYAN SALAZAR |
| Drywall Nailing | 2/2/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 2/2/2024 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 2/9/2024 | Corrections Issued | RYAN SALAZAR |
| Final | 2/9/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Final | 2/9/2024 | Not Ready for Inspection | RYAN SALAZAR |
| HVAC-Final | 2/9/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 2/9/2024 | Partial Approval | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 2/9/2024 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 2/9/2024 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 2/20/2024 | Approved | RYAN SALAZAR |
| Final | 2/20/2024 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 2/20/2024 | Approved | RYAN SALAZAR |
| HVAC-Final | 2/20/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 2/20/2024 | Approved | RYAN SALAZAR |