2100 S FIGUEROA ST 90007
Certificate Information: 2100 S FIGUEROA ST 90007
- Application / Permit
- 22016-20003-29800
- Plan Check / Job No.
- B23VN17938
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (8) Automobile Sales - new
- Work Description
- (ePlan) SUPPLEMENTAL TO PERMIT #22016-20000-29800 TO CHANGE THE PROPOSED DESIGN INCLUDING THE NEW STAIRWAY LOCATION.
- Permit Issued
- Issued on 12/17/2024
- Issuing Office
- Current Status
- Permit Finaled on 8/7/2025
Permit Application Status History
| Submitted | 2/1/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/15/2024 | YOUNG KIM |
| Corrections Issued | 3/15/2024 | YOUNG KIM |
| Quality Review Completed | 4/4/2024 | CAROLYNN NEPOMUCENO |
| Applicant returned to address corrections | 9/17/2024 | YOUNG KIM |
| Applicant returned to address corrections | 10/4/2024 | YOUNG KIM |
| Applicant returned to address corrections | 11/14/2024 | YOUNG KIM |
| Plan Check Approved | 12/15/2024 | YOUNG KIM |
| Issued | 12/17/2024 | APPLICANT |
| Permit Finaled | 8/6/2025 | ALFREDO LOPEZ |
Permit Application Clearance Information
| DAS Clearance | Cleared | 9/11/2024 | Young Kim |
Contact Information
| Architect | Architects, Orange; Lic. No.: C23757 | 1289 REAMWOOD AVE STUDIO B SUNNYVALE, CA 94089 |
| Contractor | Milan K Construction Inc; Lic. No.: 975580-B | , |
| Engineer | Labib, Funk + Associates; Lic. No.: S6625 | 319 MAIN ST EL SEGUNDO, CA 90245 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 7/10/2025 | Partial Inspection | ALFREDO LOPEZ |
| METHANE-Final | 7/10/2025 | Conditional Approval | ALFREDO LOPEZ |
| Final | 7/28/2025 | No Access for Inspection | ALFREDO LOPEZ |
| METHANE-Final | 7/28/2025 | No Access for Inspection | ALFREDO LOPEZ |
| Final | 8/6/2025 | Permit Finaled | ALFREDO LOPEZ |
| METHANE-Final | 8/6/2025 | Approved | ALFREDO LOPEZ |
| Order to Comply | 8/6/2025 | Not Required | ALFREDO LOPEZ |