11962 W COHASSET ST 91605
Certificate Information: 11962 W COHASSET ST 91605
- Application / Permit
- 22016-20002-37594
- Plan Check / Job No.
- B25VN16752
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPPLEMENTAL FOR PERMIT NUMBER # 23016-20000-01189. Change the floor plan layout from 28'-3" x 25'-11" and 680 SF. to 26'-5 1/2" x 26'-0" and 638 SF.) and to revise the structural inventory.
- Permit Issued
- Issued on 9/30/2025
- Issuing Office
- Current Status
- Permit Finaled on 1/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/11/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/26/2025 | TSE MING HUANG |
| Corrections Issued | 7/17/2025 | TSE MING HUANG |
| Quality Review Completed | 7/31/2025 | EUGENE BARBEAU |
| Plan Check Approved | 9/26/2025 | TSE MING HUANG |
| Issued | 9/30/2025 | APPLICANT |
| Permit Finaled | 1/13/2026 | ROBERTO PALACIOS-LOPEZ |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 7/25/2025 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 7/29/2025 | WALLIE JONG |
| DAS Clearance | Cleared | 7/31/2025 | Tse-Ming Huang |
| Eng Process Fee Ord 176,300 | Cleared | 7/31/2025 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 8/26/2025 | KURT CORRAL |
| Construction near power lines | Cleared | 9/3/2025 | GEVORK KARAPETYAN |
| Construction within easement | Cleared | 9/16/2025 | GEVORK KARAPETYAN |
Contact Information
| Contractor | Sauer Paul Construction; Lic. No.: 1079869-B | , |
| Engineer | Zohrevand,, Pedram; Lic. No.: C82328 | 19562 VENTURA BLVD UNIT 238 TARZANA, CA 91356 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 10/1/2025 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Green Building Final | 10/1/2025 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Green Building Rough | 10/1/2025 | Not Ready for Inspection | DEANDRE HOFFMAN |
| METHANE-Final | 10/1/2025 | Not Ready for Inspection | DEANDRE HOFFMAN |
| METHANE-Rough | 10/1/2025 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Wood Frame | 10/1/2025 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Final | 11/25/2025 | Partial Inspection | JOHN KITCKO |
| Green Building Final | 11/25/2025 | Partial Inspection | JOHN KITCKO |
| Green Building Rough | 11/25/2025 | Partial Inspection | JOHN KITCKO |
| METHANE-Final | 11/25/2025 | Partial Inspection | JOHN KITCKO |
| METHANE-Rough | 11/25/2025 | Partial Inspection | JOHN KITCKO |
| Wood Frame | 11/25/2025 | Partial Inspection | JOHN KITCKO |
| Final | 12/3/2025 | Not Ready for Inspection | KENNETH ROBERTS |
| Green Building Final | 12/3/2025 | Not Ready for Inspection | KENNETH ROBERTS |
| Green Building Rough | 12/3/2025 | Not Ready for Inspection | KENNETH ROBERTS |
| METHANE-Final | 12/3/2025 | Not Ready for Inspection | KENNETH ROBERTS |
| METHANE-Rough | 12/3/2025 | Not Ready for Inspection | KENNETH ROBERTS |
| Wood Frame | 12/3/2025 | Not Ready for Inspection | KENNETH ROBERTS |