14530 W SYLVAN ST 91411
Certificate Information: 14530 W SYLVAN ST 91411
- Application / Permit
- 22016-20002-37017
- Plan Check / Job No.
- B24VN00876
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- Supplemental permit to 22016-20000-37017 & 22016-200001-37017 to revise the use code, structural inventory and the work descriptions to read, "Tenant Improvement to the existing Protective Social Care Facility. Add/demolish non-bearing partitions, add/replace rooftop equipment pads and revise accessibility ramps." No fee Dept Error. See comments for more information.
- Permit Issued
- Issued on 3/8/2024
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 3/29/2024
Permit Application Status History
| Issued | 3/8/2024 | APPLICANT |
| Permit Finaled | 3/29/2024 | BRIAN KELLY |
Permit Application Clearance Information
| "Q" conditions | Cleared | 3/8/2024 | YINGSHI HUANG |
| CPC | Cleared | 3/8/2024 | YINGSHI HUANG |
| Miscellaneous | Cleared | 3/8/2024 | YINGSHI HUANG |
| Supp. Use District POD/CDO/TDO | Cleared | 3/8/2024 | YINGSHI HUANG |
| ZI | Cleared | 3/8/2024 | YINGSHI HUANG |
Contact Information
| Contractor | Mfi Construction Inc; Lic. No.: 902456-B | 417 E SAN BERNARDINO RD COVINA, CA 91723 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 3/21/2024 | Not Ready for Inspection | BRIAN KELLY |
| Reinforced Masonry Frame | 3/21/2024 | Approved | BRIAN KELLY |
| Special/Order Compliance | 3/26/2024 | Partial Inspection | BRIAN KELLY |
| Final | 3/27/2024 | Not Ready for Inspection | BRIAN KELLY |
| Final | 3/28/2024 | Not Ready for Inspection | BRIAN KELLY |
| Final | 3/29/2024 | No Result Entered | JEFFREY DURAN |
| Final | 3/29/2024 | Permit Finaled | BRIAN KELLY |