8210 N HASKELL AVE 91406
Certificate Information: 8210 N HASKELL AVE 91406
- Application / Permit
- 22016-20001-06671
- Plan Check / Job No.
- B22VN06560
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- eplan Supplemental permit to 22016-20000-06671 to revise parking layout to accomadate for new accessible parking stall and tenant improvement.
- Permit Issued
- Issued on 8/30/2022
- Issuing Office
- Current Status
- CofO Issued on 1/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2022 | MICHAEL LOPEZ |
| Corrections Issued | 5/27/2022 | MICHAEL LOPEZ |
| Quality Review Completed | 6/3/2022 | SAI KHUM |
| Plan Check Approved | 8/26/2022 | MICHAEL LOPEZ |
| Issued | 8/30/2022 | APPLICANT |
| CofO in Progress | 1/11/2023 | DEANDRE HOFFMAN |
| CofO in Progress | 1/11/2023 | DEANDRE HOFFMAN |
| Permit Finaled | 1/11/2023 | JEFFREY DURAN |
| CofO Issued | 1/11/2023 | JEFFREY DURAN |
| Permit Finaled | 1/11/2023 | JEFFREY DURAN |
Permit Application Clearance Information
| Low Impact Development | Cleared | 5/31/2022 | MARTIN FRAGOSO |
| Prkng lot landscape/Water mgmt | Cleared | 7/26/2022 | SPENCER WEJROWSKI |
| DAS Clearance | Cleared | 8/18/2022 | Michael Perez |
Contact Information
| Architect | Machulsky,, Darren Lee; Lic. No.: C30817 | 3508 WOODLAND WAY CARLSBAD, CA 92008 |
| Contractor | S & P Construction Services; Lic. No.: 974245-B | 4760 DEVONPORT CIRCLE YORBA LINDA, CA 92887 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 9/12/2022 | Approved | JEFFREY FULTON |
| Drywall Nailing | 9/13/2022 | No Access for Inspection | JEFFREY FULTON |
| Final | 10/25/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Reinforced Masonry Frame | 10/25/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Final | 10/31/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Reinforced Masonry Frame | 10/31/2022 | Approved | JEFFREY FULTON |
| Final | 11/3/2022 | Corrections Issued | DANIEL VARNUM |
| Final | 11/8/2022 | Corrections Issued | JEFFREY FULTON |
| Special/Order Compliance | 11/8/2022 | Partial Inspection | DEANDRE HOFFMAN |
| Final | 1/3/2023 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Final | 1/6/2023 | Conditional Approval | DEANDRE HOFFMAN |
| Final | 1/11/2023 | OK to Issue CofO | DEANDRE HOFFMAN |