8210 N HASKELL AVE 91406

Certificate Information: 8210 N HASKELL AVE 91406

Application / Permit
22016-20001-06671
Plan Check / Job No.
B22VN06560
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
eplan Supplemental permit to 22016-20000-06671 to revise parking layout to accomadate for new accessible parking stall and tenant improvement.
Permit Issued
Issued on 8/30/2022
Issuing Office
Current Status
CofO Issued on 1/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/28/2022 APPLICANT
Assigned to Plan Check Engineer 5/19/2022 MICHAEL LOPEZ
Corrections Issued 5/27/2022 MICHAEL LOPEZ
Quality Review Completed 6/3/2022 SAI KHUM
Plan Check Approved 8/26/2022 MICHAEL LOPEZ
Issued 8/30/2022 APPLICANT
CofO in Progress 1/11/2023 DEANDRE HOFFMAN
CofO in Progress 1/11/2023 DEANDRE HOFFMAN
Permit Finaled 1/11/2023 JEFFREY DURAN
CofO Issued 1/11/2023 JEFFREY DURAN
Permit Finaled 1/11/2023 JEFFREY DURAN

Permit Application Clearance Information

Low Impact Development Cleared 5/31/2022 MARTIN FRAGOSO
Prkng lot landscape/Water mgmt Cleared 7/26/2022 SPENCER WEJROWSKI
DAS Clearance Cleared 8/18/2022 Michael Perez

Contact Information

Architect Machulsky,, Darren Lee; Lic. No.: C30817 3508 WOODLAND WAY      CARLSBAD, CA 92008
Contractor S & P Construction Services; Lic. No.: 974245-B 4760 DEVONPORT CIRCLE      YORBA LINDA, CA 92887

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Drywall Nailing 9/12/2022 Approved JEFFREY FULTON
Drywall Nailing 9/13/2022 No Access for Inspection JEFFREY FULTON
Final 10/25/2022 Not Ready for Inspection JEFFREY FULTON
Reinforced Masonry Frame 10/25/2022 Not Ready for Inspection JEFFREY FULTON
Final 10/31/2022 Not Ready for Inspection JEFFREY FULTON
Reinforced Masonry Frame 10/31/2022 Approved JEFFREY FULTON
Final 11/3/2022 Corrections Issued DANIEL VARNUM
Final 11/8/2022 Corrections Issued JEFFREY FULTON
Special/Order Compliance 11/8/2022 Partial Inspection DEANDRE HOFFMAN
Final 1/3/2023 Not Ready for Inspection DEANDRE HOFFMAN
Final 1/6/2023 Conditional Approval DEANDRE HOFFMAN
Final 1/11/2023 OK to Issue CofO DEANDRE HOFFMAN