22627 W COVELLO ST 91307

Certificate Information: 22627 W COVELLO ST 91307

Application / Permit
22016-20001-04454
Plan Check / Job No.
B23VN01089
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SUPPL TO PERMIT TO 22016-20000-04454 TO REVISE PLAN IN ENTIRELY & CHANGE WORK DESCRIPTION TO STATE, "CONVERT EX 20'X20' DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d) WITH 10'-0" x 20'-0" ADDITION AT FIRST FLOOR AND 30'-0" x 20'-0" SECOND STORY ADDITION." SEE COMMENTS.
Permit Issued
Issued on 7/7/2023
Issuing Office
Valley
Current Status
Permit Finaled on 12/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/30/2023 APPLICANT
Assigned to Plan Check Engineer 2/10/2023 HAYATO TSUCHIYA
Corrections Issued 2/11/2023 HAYATO TSUCHIYA
Building Plans Picked Up 2/13/2023 APPLICANT
Applicant returned to address corrections 6/8/2023 JESSE ARELLANO
Applicant returned to address corrections 6/21/2023 SERGIO MUNIZ
Applicant returned to address corrections 7/5/2023 MOHAMMAD ESMAILI
Plan Check Approved 7/7/2023 SARKIS HARABEDIAN
Issued 7/7/2023 APPLICANT
Permit Finaled-Status Void 8/24/2023 JEFFREY HARTLINE
Re-Activate Permit 8/31/2023 HORACE FULTZ
Permit Finaled 12/7/2023 JEFFREY HARTLINE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/27/2023 MEGAN GODINEZ
Low Impact Development (LID) Cleared 3/23/2023 TOMMY YIN
Sewer availability Cleared 3/23/2023 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 3/31/2023 MEGAN GODINEZ
Construction near power lines Cleared 7/1/2023 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,
Engineer Hajdari,, Genti; Lic. No.: C88031 140 S MENTOR AVE APT #207      PASADENA, CA 91106

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/11/2023 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 8/11/2023 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 8/11/2023 Partial Approval VINCENT HANLEY
Deputy Drilled-In Anchors 8/14/2023 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 8/17/2023 Approved CHRIS CHRISTENSEN
Deputy Wood Construction 9/20/2023 Conditional Approval JEFFREY HARTLINE
BUILDING-Rough-Frame 9/27/2023 Corrections Issued JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 9/27/2023 Corrections Issued JEFFREY HARTLINE
Green Building Rough 9/27/2023 Approved JEFFREY HARTLINE
Rough-Elec/Plmb/HVAC 9/27/2023 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 10/3/2023 Approved JEFFREY HARTLINE
Drywall Nailing 12/7/2023 Approved JEFFREY HARTLINE
Final 12/7/2023 Permit Finaled JEFFREY HARTLINE
Green Building Final 12/7/2023 Approved JEFFREY HARTLINE
Smoke Detectors 12/7/2023 Approved JEFFREY HARTLINE