2958 S 11TH AVE 90018
Certificate Information: 2958 S 11TH AVE 90018
- Application / Permit
- 22016-20000-39252
- Plan Check / Job No.
- B22VN19144
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert detached garage to Accessory Dwelling Unit
- Permit Issued
- Issued on 1/12/2023
- Issuing Office
- Current Status
- CofO Issued on 11/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/4/2023 | SERGIO MUNIZ |
| Corrections Issued | 1/5/2023 | SERGIO MUNIZ |
| Building Plans Picked Up | 1/6/2023 | APPLICANT |
| Applicant returned to address corrections | 1/11/2023 | HAYATO TSUCHIYA |
| Plan Check Approved | 1/12/2023 | ALEC MOUSAKHANIAN |
| Issued | 1/12/2023 | APPLICANT |
| CofO in Progress | 11/6/2023 | CALEB MEISTER |
| Permit Finaled | 11/18/2023 | DEROLD HAUFF |
| CofO Issued | 11/18/2023 | DEROLD HAUFF |
| Permit Finaled | 11/18/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/10/2023 | CELINA MORENO |
| Sewer availability | Cleared | 1/10/2023 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 1/12/2023 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/3/2023 | Partial Inspection | CALEB MEISTER |
| Footing/Foundation/Slab | 5/16/2023 | Approved | CALEB MEISTER |
| Underground Mechanical | 5/16/2023 | Partial Approval | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2023 | Corrections Issued | CALEB MEISTER |
| Green Building Rough | 6/5/2023 | Not Ready for Inspection | CALEB MEISTER |
| Underground Mechanical | 6/5/2023 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 6/12/2023 | Corrections Issued | CALEB MEISTER |
| ELECTRICAL-Rough | 6/12/2023 | Corrections Issued | CALEB MEISTER |
| Green Building Rough | 6/12/2023 | Not Ready for Inspection | CALEB MEISTER |
| HVAC-Rough | 6/12/2023 | Corrections Issued | CALEB MEISTER |
| PLUMBING-Rough | 6/12/2023 | Corrections Issued | CALEB MEISTER |
| BUILDING-Rough-Frame | 6/20/2023 | Approved | CALEB MEISTER |
| ELECTRICAL-Rough | 6/20/2023 | Approved | CALEB MEISTER |
| Green Building Rough | 6/20/2023 | Approved | CALEB MEISTER |
| HVAC-Rough | 6/20/2023 | Approved | CALEB MEISTER |
| Insulation | 6/20/2023 | Corrections Issued | CALEB MEISTER |
| Interior/Exterior Lathing | 6/20/2023 | Approved | CALEB MEISTER |
| PLUMBING-Rough | 6/20/2023 | Approved | CALEB MEISTER |
| Drywall Nailing | 7/3/2023 | Approved | CALEB MEISTER |
| Shower Pan | 7/3/2023 | Not Ready for Inspection | CALEB MEISTER |
| Final | 8/17/2023 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Final | 8/17/2023 | Not Ready for Inspection | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 8/17/2023 | SGSOV Not Ready | CALEB MEISTER |
| Smoke Detectors | 8/17/2023 | Not Ready for Inspection | CALEB MEISTER |
| Final | 11/6/2023 | OK to Issue CofO | CALEB MEISTER |
| Green Building Final | 11/6/2023 | Approved | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 11/6/2023 | SGSOV Approved | CALEB MEISTER |
| Smoke Detectors | 11/6/2023 | Approved | CALEB MEISTER |