4959 N CARTWRIGHT AVE 91601
Certificate Information: 4959 N CARTWRIGHT AVE 91601
- Application / Permit
- 22016-20000-39156
- Plan Check / Job No.
- B22VN19096
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR AND EXTERIOR REMODEL TO THE (E) SFD. RE-FRAME THE (E) FRONT PORCH, CONVERT THE REAR PORCH INTO LIVING SPACE, REMOVE INTERIOR WALLS TO ENLARGE THE (E) KITCHEN, REMODEL LIVING/DINING ROOM AREA AND RECONFIGURE THE LAYOUT WITH NEW WINDOWS AND DOORS. WORK PER ENGINEER.
- Permit Issued
- Issued on 6/21/2023
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 10/22/2024
Permit Application Status History
| Submitted | 12/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2022 | ANGELICA DAVE |
| Plan Check Approved | 12/29/2022 | ANGELICA MARTINEZ |
| Plan Check Approved | 12/29/2022 | GURUNATH NESARAJAH |
| Issued | 6/21/2023 | APPLICANT |
| Permit Finaled | 10/21/2024 | ROBERTO PALACIOS-LOPEZ |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Agaian,, Raffi; Lic. No.: C32156 | 2234 DEL MAR ROAD UNIT # 1 MONTROSE, CA 91020 |
| Contractor | Owner-Builder | , |
| Engineer | Karapetian,, Arbi; Lic. No.: C79953 | 6854 FOOTHILL BLVD TUJUNGA, CA 91042 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/6/2023 | Corrections Issued | JUAN VALENZUELA |
| Footing/Foundation/Slab | 7/10/2023 | Partial Approval | JOHN HAYES |
| Wood Frame | 7/17/2023 | Partial Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 8/8/2023 | Corrections Issued | JOHN HAYES |
| HVAC-Rough | 8/8/2023 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 8/8/2023 | Not Ready for Inspection | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 8/8/2023 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 8/11/2023 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 8/11/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 8/11/2023 | Approved | JACK KARGODORIAN |
| Insulation | 8/21/2023 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 8/21/2023 | Partial Approval | THOMAS FINNILA |
| Shower Pan | 8/24/2023 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 8/28/2023 | Approved | JOHN HAYES |
| Deputy Drilled-In Anchors | 9/11/2023 | Conditional Approval | JOHN HAYES |
| Footing/Foundation/Slab | 9/13/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 9/21/2023 | Approved | JOHN HAYES |
| Insulation | 10/10/2023 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/19/2023 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2023 | Approved | JENNIFER RABUCHIN |
| Rough-Elec/Plmb/HVAC | 10/19/2023 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/24/2023 | Approved | JENNIFER RABUCHIN |
| Insulation | 10/24/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 10/24/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/24/2023 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 10/30/2023 | Approved | RYAN SALAZAR |
| Final | 10/15/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 10/15/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 10/15/2024 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 10/15/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 10/21/2024 | Permit Finaled | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 10/21/2024 | Approved | ROBERTO PALACIOS-LOPEZ |