7321 N CIRRUS WAY 91307
Certificate Information: 7321 N CIRRUS WAY 91307
- Application / Permit
- 22016-20000-38909
- Plan Check / Job No.
- B22VN18915
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan Interior remodeling Convert portion of (E) garage to 1 bedroom, 1 bathroom and powder room. Relocate kitchen and laundry room.
- Permit Issued
- Issued on 2/3/2023
- Issuing Office
- Current Status
- CofO Issued on 12/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/28/2022 | KHUONG TRUONG |
| Corrections Issued | 12/28/2022 | KHUONG TRUONG |
| Applicant returned to address corrections | 1/13/2023 | JOSEPH RAFOLS |
| Plan Check Approved | 1/27/2023 | JOSEPH RAFOLS |
| Issued | 2/3/2023 | APPLICANT |
| CofO in Progress | 12/13/2024 | JEFFREY HARTLINE |
| CofO Issued | 12/30/2024 | JOHN JANSON |
| Permit Finaled | 12/30/2024 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/17/2023 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 1/24/2023 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 1/24/2023 | JOSE DUARTE-DIAZ |
| Public Works-Open Permits | Cleared | 1/24/2023 | JOSE DUARTE-DIAZ |
| Public Works-Sewers | Cleared | 1/24/2023 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 9/7/2023 | Corrections Issued | JEFFREY HARTLINE |
| HVAC-Rough | 9/7/2023 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 9/7/2023 | Approved | JEFFREY HARTLINE |
| Underground Mechanical | 9/7/2023 | Approved | JEFFREY HARTLINE |
| Deputy Drilled-In Anchors | 9/20/2023 | Conditional Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 9/21/2023 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 9/21/2023 | Approved | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 9/21/2023 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 9/21/2023 | Approved | JEFFREY HARTLINE |
| Insulation | 9/22/2023 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 9/29/2023 | Approved | VINCENT HANLEY |
| Shower Pan | 9/29/2023 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 10/17/2023 | Approved | JEFFREY HARTLINE |
| Final | 8/29/2024 | Corrections Issued | JEFFREY HARTLINE |
| Green Building Final | 8/29/2024 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 8/29/2024 | SGSOV Approved | JEFFREY HARTLINE |
| Smoke Detectors | 8/29/2024 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Final | 12/12/2024 | Approved | JEFFREY HARTLINE |
| Final | 12/12/2024 | OK to Issue CofO | JEFFREY HARTLINE |
| HVAC-Final | 12/12/2024 | Approved | JEFFREY HARTLINE |
| PLUMBING-Final | 12/12/2024 | Approved | JEFFREY HARTLINE |