8939 N SYLMAR AVE 91402
Certificate Information: 8939 N SYLMAR AVE 91402
- Application / Permit
- 22016-20000-38903
- Plan Check / Job No.
- B22VN18912
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan EXISTING GARAGE REMODELING AND ADDITION (NEW STORAGE) ALL WORK DONE PER WFPP
- Permit Issued
- Issued on 3/9/2023
- Issuing Office
- Current Status
- CofO Issued on 1/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/27/2022 | KHUONG TRUONG |
| Corrections Issued | 12/27/2022 | KHUONG TRUONG |
| Applicant returned to address corrections | 1/4/2023 | RACHEL BEYENE |
| Applicant returned to address corrections | 1/5/2023 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 1/17/2023 | MOHAMMAD ESMAILI |
| Plan Check Approved | 3/8/2023 | MOHAMMAD ESMAILI |
| Issued | 3/9/2023 | APPLICANT |
| CofO in Progress | 12/5/2023 | GREGG CUMMINGS |
| Permit Finaled | 1/3/2024 | RUBEN SALAS |
| CofO Issued | 1/3/2024 | RUBEN SALAS |
| Permit Finaled | 1/3/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/28/2022 | LUCIA MERCADO |
| Eng Process Fee Ord 176,300 | Cleared | 12/29/2022 | LUCIA MERCADO |
| Public Works-Highway Ded. | Cleared | 12/29/2022 | LUCIA MERCADO |
| Public Works-Open Permits | Cleared | 12/29/2022 | LUCIA MERCADO |
| Public Works-Sewers | Cleared | 12/29/2022 | LUCIA MERCADO |
Contact Information
| Contractor | Markarian Setrag; Lic. No.: 832632-B | , |
| Contractor | Pampa Investment Inc; Lic. No.: 832632-B | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/3/2023 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 5/12/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 8/2/2023 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 8/9/2023 | Not Ready for Inspection | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 8/9/2023 | Approved | DAVID MATSON |
| BUILDING-Rough-Frame | 8/22/2023 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Final | 8/22/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2023 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 8/29/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 9/8/2023 | Approved | MICHEL ABAJAN |
| Final | 11/20/2023 | Corrections Issued | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 11/20/2023 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 11/20/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 11/30/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 11/30/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 12/4/2023 | Approved | GREGG CUMMINGS |
| Final | 12/4/2023 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 12/4/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 12/4/2023 | Approved | GREGG CUMMINGS |