19709 W RINALDI ST 91326
Certificate Information: 19709 W RINALDI ST 91326
- Application / Permit
- 22016-20000-38868
- Plan Check / Job No.
- B22VN18898
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Medical Office
- Work Description
- ePlan Change of use from Retail to Dermatology office.
- Permit Issued
- Issued on 5/18/2023
- Issuing Office
- Current Status
- CofO Issued on 1/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2023 | KAVIAN REFAHI |
| Corrections Issued | 1/22/2023 | KAVIAN REFAHI |
| Quality Review Completed | 1/26/2023 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 2/28/2023 | KAVIAN REFAHI |
| Plan Check Approved | 5/9/2023 | KAVIAN REFAHI |
| Issued | 5/18/2023 | APPLICANT |
| CofO in Progress | 1/22/2024 | DEANDRE HOFFMAN |
| Permit Finaled | 1/23/2024 | JEFFREY DURAN |
| CofO Issued | 1/23/2024 | JEFFREY DURAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/28/2023 | CARLOS AGUILERA |
| Specific Plan | Cleared | 3/9/2023 | SHEILA AHORAIAN |
| "D" conditions | Cleared | 3/14/2023 | ASHLEY RODARTE |
| Miscellaneous | Cleared | 3/14/2023 | ASHLEY RODARTE |
| ZA Case | Cleared | 3/14/2023 | ASHLEY RODARTE |
| Specific Plan | Cleared | 4/6/2023 | CLAUDIA RODRIGUEZ |
| DAS Clearance | Cleared | 5/2/2023 | Hernan Arreola |
Contact Information
| Architect | Parezo,, John Allen; Lic. No.: C15656 | 5949 WOODLAND VIEW DRIVE WOODLAND HILLS, CA 91367 |
| Architect | Parezo,, John Allen; Lic. No.: NA15656 | , |
| Contractor | Intertex General Contractors Inc; Lic. No.: 482946-B | , |
| Contractor | Intertex Inc; Lic. No.: 482946-B | , |
| Engineer | Rosepink,, Dustin; Lic. No.: NA5885 | , |
| Engineer | Rosepink,, Dustin; Lic. No.: S5885 | 24255 VIA MADRUGADA MISSION VIEJO, CA 92692 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/28/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Footing/Foundation/Slab | 6/30/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Light Gage Steel Frame | 7/18/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Wood Frame | 7/18/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Light Gage Steel Frame | 7/28/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Drywall Nailing | 8/2/2023 | Partial Inspection | DEANDRE HOFFMAN |
| T-Bar Ceiling | 9/12/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Final | 1/11/2024 | Corrections Issued | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 1/11/2024 | SGSOV Approved | DEANDRE HOFFMAN |
| Smoke Detectors | 1/11/2024 | Approved | DEANDRE HOFFMAN |
| Final | 1/22/2024 | OK to Issue CofO | DEANDRE HOFFMAN |