760 S WESTHOLME AVE 90024
Certificate Information: 760 S WESTHOLME AVE 90024
- Application / Permit
- 22016-20000-38733
- Plan Check / Job No.
- B22VN18782
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL OF (E) SINGLE FAMILY DWELLING ALL WORK PER ENGINEERING ALL WORK PER ENGINEERING TO PROVIDE NEW BEAM ON 3RD FLOOR AND NEW CEILING JOISTS NO CHANGE IN HEIGHT, FOOTPRINT OR AREA OR FLOORPLANS
- Permit Issued
- Issued on 3/10/2023
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 10/5/2023
Permit Application Status History
| Submitted | 12/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2023 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 1/10/2023 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 1/11/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 1/13/2023 | APPLICANT |
| Plan Check Approved | 3/9/2023 | SEWADA ZADOORAN MILAGARDI |
| Issued | 3/10/2023 | APPLICANT |
| Permit Finaled | 10/5/2023 | STEPHANIE SWANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/18/2023 | MANUEL TEJADA |
| Eng Process Fee Ord 176,300 | Cleared | 1/23/2023 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 1/23/2023 | DINAH GARIN |
| Sewer availability | Cleared | 1/23/2023 | DINAH GARIN |
Contact Information
| Contractor | Yaghoubi M Corp; Lic. No.: 972773-B | 6459 LUBAO AVENUE WOODLAND HILLS, CA 91367 |
| Engineer | Alexander,, Andy; Lic. No.: C84086 | 1615 GRAMERCY AVE TORRANCE, CA 90501 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 3/13/2023 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 3/13/2023 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 3/13/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 3/13/2023 | Conditional Approval | STEPHANIE SWANSON |
| Shower Pan | 3/13/2023 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 4/10/2023 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 4/10/2023 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 4/17/2023 | Partial Approval | STEPHANIE SWANSON |
| Insulation | 4/17/2023 | Conditional Approval | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 4/17/2023 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 5/1/2023 | Partial Approval | STEPHANIE SWANSON |
| Drywall Nailing | 5/2/2023 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 5/2/2023 | Conditional Approval | CHRISTOPHER WILSON |
| Structural Steel Frame | 5/2/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Special/Order Compliance | 9/26/2023 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 9/27/2023 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 9/27/2023 | Corrections Issued | STEPHANIE SWANSON |
| Final | 9/27/2023 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Final | 9/27/2023 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 9/27/2023 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 9/27/2023 | Corrections Issued | STEPHANIE SWANSON |
| Smoke Detectors | 9/27/2023 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 10/2/2023 | Corrections Issued | STEPHANIE SWANSON |
| Final | 10/2/2023 | Corrections Issued | STEPHANIE SWANSON |
| Gas Test | 10/2/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| HVAC-Final | 10/2/2023 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 10/2/2023 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 10/2/2023 | Corrections Issued | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 10/2/2023 | SGSOV Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 10/5/2023 | Approved | STEPHANIE SWANSON |
| Final | 10/5/2023 | Permit Finaled | STEPHANIE SWANSON |
| Gas Test | 10/5/2023 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 10/5/2023 | Approved | STEPHANIE SWANSON |