18435 W NAPA ST 91325

Certificate Information: 18435 W NAPA ST 91325

Application / Permit
22016-20000-38694
Plan Check / Job No.
B22VN18749
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(12) Perfume Manufacturing
Work Description
TI TO INFILL 3 STORY SHELL BUILDING; LEVEL 2 BECOMES PERFUME MANUFACTURING AND LEVEL 3 BECOMES OFFICE; LEVEL 1 PARKING TO STAY THE SAME
Permit Issued
Issued on 6/27/2024
Issuing Office
Current Status
CofO Issued on 4/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/22/2022 APPLICANT
Assigned to Plan Check Engineer 1/12/2023 SEAN SHAHMIRI
Corrections Issued 1/17/2023 SEAN SHAHMIRI
Quality Review Completed 1/19/2023 OMID HEDAYAT
Applicant returned to address corrections 4/4/2023 SEAN SHAHMIRI
Applicant returned to address corrections 5/30/2023 SEAN SHAHMIRI
Plan Check Approved 7/31/2023 SEAN SHAHMIRI
Issued 6/27/2024 APPLICANT
Permit Finaled 4/10/2026 JEFFREY DURAN
CofO Issued 4/10/2026 JEFFREY DURAN
Permit Finaled 4/10/2026 JEFFREY DURAN

Permit Application Clearance Information

Green Code Cleared 3/30/2023 MICHAEL AYERS
"Q" conditions Cleared 4/4/2023 KENTON TRINH
Eng Process Fee Ord 176,300 Cleared 4/4/2023 LEE GUILBEAUX
Sewer availability Cleared 4/4/2023 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 4/4/2023 LEE GUILBEAUX
Public Works-Sewers Cleared 4/4/2023 LEE GUILBEAUX
Chemical processes Cleared 7/10/2023 SCAQMD APPROVED
DAS Clearance Cleared 7/26/2023 Ricardo Ramirez Solis

Contact Information

Architect Kittipongdaja,, Pisuttisuk; Lic. No.: C38763 1930 GEORGIA CT #10      SAN DIEGO, CA 92104
Contractor Conex Development Company Inc; Lic. No.: 449347-B       ,
Engineer Nagarajan,, Sivaram; Lic. No.: S6349 167 MATISSE CIRCLE      ALISO VIEJO, CA 92656

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 8/2/2024 Partial Approval DEANDRE HOFFMAN
Green Building Rough 4/28/2025 Not Ready for Inspection KENNETH ROBERTS
Wood Frame 4/28/2025 Not Ready for Inspection KENNETH ROBERTS
Green Building Rough 7/9/2025 Partial Inspection DEANDRE HOFFMAN
Wood Frame 7/9/2025 Partial Approval DEANDRE HOFFMAN
Drywall Nailing 7/18/2025 Partial Approval DEANDRE HOFFMAN
Drywall Nailing 8/1/2025 Partial Approval DEANDRE HOFFMAN
Green Building Rough 8/1/2025 Partial Inspection DEANDRE HOFFMAN
Insulation 8/1/2025 Approved DEANDRE HOFFMAN
Wood Frame 8/1/2025 Partial Approval DEANDRE HOFFMAN
Drywall Nailing 8/8/2025 Corrections Issued DEANDRE HOFFMAN
Drywall Nailing 8/19/2025 Partial Approval DEANDRE HOFFMAN
Notice of Violation 8/19/2025 Not Required DEANDRE HOFFMAN
Drywall Nailing 9/2/2025 Approved DEANDRE HOFFMAN
Interior/Exterior Lathing 9/5/2025 Approved DEANDRE HOFFMAN
T-Bar Ceiling 11/14/2025 Approved DEANDRE HOFFMAN
Final 3/5/2026 Not Ready for Inspection EDWIN GREGORYONA
Green Building Final 3/5/2026 Not Ready for Inspection EDWIN GREGORYONA
Green Building Rough 3/5/2026 Not Ready for Inspection EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 3/5/2026 SGSOV Not Ready EDWIN GREGORYONA
Smoke Detectors 3/5/2026 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 3/5/2026 Not Ready for Inspection EDWIN GREGORYONA
Final 3/12/2026 Partial Inspection EDWIN GREGORYONA
Green Building Final 3/12/2026 Approved EDWIN GREGORYONA
Green Building Rough 3/12/2026 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 3/12/2026 SGSOV Approved EDWIN GREGORYONA
Smoke Detectors 3/12/2026 Approved EDWIN GREGORYONA
Wood Frame 3/12/2026 Approved EDWIN GREGORYONA
Final 4/3/2026 Conditional Approval EDWIN GREGORYONA