20825 W SHERMAN WAY 91306

Certificate Information: 20825 W SHERMAN WAY 91306

Application / Permit
22016-20000-38454
Plan Check / Job No.
B22VN18593
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(18) Day Care Facility adults
Work Description
EPLAN ** CONVERT EXISTING 7,640 S.F. FIRST LEVEL AREA INTO ADULT DAYCARE HEALTH CENTER.
Permit Issued
Issued on 11/30/2023
Issuing Office
Current Status
CofO Corrected on 5/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/11/2023 APPLICANT
Assigned to Plan Check Engineer 2/2/2023 KAVIAN REFAHI
Corrections Issued 2/6/2023 KAVIAN REFAHI
Quality Review Completed 2/15/2023 CHIHARU SUZUKI
Applicant returned to address corrections 9/11/2023 KAVIAN REFAHI
Applicant returned to address corrections 9/22/2023 KAVIAN REFAHI
Plan Check Approved 10/2/2023 KAVIAN REFAHI
Issued 11/30/2023 APPLICANT
CofO in Progress 5/23/2025 GREGORY POMISH
CofO in Progress 5/23/2025 GREGORY POMISH
CofO Issued-Status Void 5/23/2025 JEFFREY DURAN
Permit Finaled-Status Void 5/23/2025 JEFFREY DURAN
Re-Activate Permit 5/28/2025 RICKEY JACKSON
CofO Corrected 5/30/2025 RICKEY JACKSON
Permit Finaled 5/30/2025 RICKEY JACKSON

Permit Application Clearance Information

"Q" conditions Cleared 7/12/2023 LOUIS ORTEGA
ZA Case Cleared 7/12/2023 LOUIS ORTEGA
Fire Marshal Fire Life Safety Cleared 7/18/2023 ANDREW KO
Sewer availability Cleared 8/3/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 8/9/2023 DAGOVERTO GUERRERO
DAS Clearance Cleared 8/11/2023 Joe Vo
ZA Case Cleared 8/18/2023 LOUIS ORTEGA
Green Code Cleared 8/23/2023 MICHAEL AYERS

Contact Information

Contractor David Sahakyan; Lic. No.: 1109805-B       ,
Engineer Martirossyan,, Armen; Lic. No.: C64223 802 PORTOLA AVE      GLENDALE, CA 91206

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/16/2024 Conditional Approval DEANDRE HOFFMAN
Footing/Foundation/Slab 2/8/2024 Approved DEANDRE HOFFMAN
Special/Order Compliance 2/8/2024 Corrections Issued DEANDRE HOFFMAN
Deputy Drilled-In Anchors 3/26/2024 Conditional Approval DEANDRE HOFFMAN
Footing/Foundation/Slab 3/27/2024 Not Ready for Inspection DEANDRE HOFFMAN
Green Building Rough 7/15/2024 Not Ready for Inspection GREGORY POMISH
Wood Frame 7/15/2024 Not Ready for Inspection GREGORY POMISH
Deputy Wood Construction 7/16/2024 Conditional Approval GREGORY POMISH
Green Building Rough 7/19/2024 Partial Inspection DEANDRE HOFFMAN
Wood Frame 7/19/2024 Partial Approval DEANDRE HOFFMAN
Wood Frame 10/24/2024 Partial Approval DEANDRE HOFFMAN
Drywall Nailing 11/7/2024 Approved DEANDRE HOFFMAN
Special/Order Compliance 11/7/2024 Corrections Issued DEANDRE HOFFMAN
T-Bar Ceiling 11/7/2024 Approved DEANDRE HOFFMAN
Final 4/22/2025 Not Ready for Inspection DEANDRE HOFFMAN
Green Building Final 4/22/2025 Approved DEANDRE HOFFMAN
Green Building Rough 4/22/2025 Approved DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 4/22/2025 SGSOV Not Ready DEANDRE HOFFMAN
Smoke Detectors 4/22/2025 Approved DEANDRE HOFFMAN
Wood Frame 4/22/2025 Approved DEANDRE HOFFMAN
Final 5/1/2025 Partial Inspection DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 5/1/2025 SGSOV Approved DEANDRE HOFFMAN
Special/Order Compliance 5/9/2025 Partial Inspection GREGORY POMISH
Final 5/23/2025 OK to Issue CofO GREGORY POMISH