6713 N CAPPS AVE 91335

Certificate Information: 6713 N CAPPS AVE 91335

Application / Permit
22016-20000-38449
Plan Check / Job No.
B22VN18585
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan : Converting detached garage into ADU per state law.
Permit Issued
Issued on 9/14/2023
Issuing Office
Current Status
CofO Issued on 6/20/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2022 APPLICANT
Assigned to Plan Check Engineer 12/27/2022 RICARDO RAMIREZ
Corrections Issued 12/27/2022 RICARDO RAMIREZ
Applicant returned to address corrections 8/30/2023 DANIEL YIP
Applicant returned to address corrections 9/1/2023 DANIEL YIP
Plan Check Approved 9/12/2023 DANIEL YIP
Issued 9/14/2023 APPLICANT
CofO in Progress 6/18/2024 JEFFREY BULL
Permit Finaled 6/20/2024 JOHN JANSON
CofO Issued 6/20/2024 JOHN JANSON
Permit Finaled 6/20/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/11/2023 COLIN LOREDO
Sewer availability Cleared 1/11/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 1/12/2023 COLIN LOREDO
Construction near power lines Cleared 5/5/2023 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,
Engineer Babapirzadeh,, Ghazal; Lic. No.: C90480 7270 HILLSIDE AVE   APT 306    LOS ANGELES, CA 90046

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/29/2023 Approved JEFFREY BULL
Footing/Foundation/Slab 1/3/2024 Approved JEFFREY BULL
BUILDING-Rough-Frame 1/26/2024 Not Ready for Inspection KRISTEN CAUSEY
ELECTRICAL-Rough 1/26/2024 Approved KRISTEN CAUSEY
HVAC-Rough 1/26/2024 Approved KRISTEN CAUSEY
PLUMBING-Rough 1/26/2024 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 1/30/2024 Not Ready for Inspection JEFFREY BULL
Insulation 1/30/2024 Corrections Issued JEFFREY BULL
BUILDING-Rough-Frame 2/6/2024 Approved VINCENT HANLEY
Drywall Nailing 2/6/2024 Approved VINCENT HANLEY
Green Building Rough 2/6/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 2/6/2024 Partial Approval VINCENT HANLEY
Sewer 2/28/2024 Corrections Issued HENRY KIM
Underground Mechanical 2/28/2024 Approved HENRY KIM
Interior/Exterior Lathing 3/5/2024 Approved JEFFREY BULL
PLUMBING-Final 3/5/2024 Approved JEFFREY BULL
Service/Power Release 3/5/2024 Approved JEFFREY BULL
Final 3/11/2024 Corrections Issued JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 3/11/2024 SGSOV Approved JEFFREY BULL
Smoke Detectors 3/11/2024 Approved JEFFREY BULL
Final 6/18/2024 OK to Issue CofO JEFFREY BULL