10649 N LAS LUNITAS AVE 91042
Certificate Information: 10649 N LAS LUNITAS AVE 91042
- Application / Permit
- 22016-20000-38286
- Plan Check / Job No.
- B22VN18527
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Convert (E) detached 2- Car Garage into ADU per ordinance.
- Permit Issued
- Issued on 7/8/2023
- Issuing Office
- Current Status
- CofO Issued on 12/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2023 | KHUONG TRUONG |
| Corrections Issued | 1/8/2023 | KHUONG TRUONG |
| Applicant returned to address corrections | 5/4/2023 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 5/19/2023 | FARSHAD ALIMOHAMADI |
| Issued | 7/8/2023 | APPLICANT |
| CofO in Progress | 12/11/2023 | WILLIAM WREN |
| Permit Finaled | 12/28/2023 | RUBEN SALAS |
| CofO Issued | 12/28/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/1/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 5/1/2023 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 5/9/2023 | LEE GUILBEAUX |
| Tenant Habitability Plan | Cleared | 5/9/2023 | ISMAEL HERNANDEZ |
| Grading Pre-Inspection | Cleared | 5/16/2023 | BRIAN MILLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Saiyadian, Sarnaghi, Tomik; Lic. No.: C89129 | 1171 JUSTIN AVE APT 3 GLENDALE, CA 91201 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/25/2023 | Conditional Approval | WILLIAM WREN |
| Footing/Foundation/Slab | 7/28/2023 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 7/28/2023 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 9/1/2023 | Not Ready for Inspection | DAVID ANDERSON |
| HVAC-Rough | 9/1/2023 | Not Ready for Inspection | DAVID ANDERSON |
| PLUMBING-Rough | 9/1/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Wood Frame | 9/1/2023 | Not Ready for Inspection | DAVID ANDERSON |
| BUILDING-Rough-Frame | 9/7/2023 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 9/7/2023 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2023 | Approved | WILLIAM WREN |
| HVAC-Rough | 9/7/2023 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 9/7/2023 | Approved | WILLIAM WREN |
| Insulation | 9/29/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 9/29/2023 | Approved | WILLIAM WREN |
| Underground Mechanical | 9/29/2023 | Approved | WILLIAM WREN |
| Drywall Nailing | 10/19/2023 | Approved | WILLIAM WREN |
| Shower Pan | 10/19/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 11/3/2023 | Approved | WILLIAM WREN |
| Final | 11/17/2023 | Corrections Issued | WILLIAM WREN |
| Green Building Final | 11/17/2023 | Approved | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 11/17/2023 | SGSOV Approved | WILLIAM WREN |
| Smoke Detectors | 11/17/2023 | Approved | WILLIAM WREN |
| Final | 11/27/2023 | OK to Issue CofO | WILLIAM WREN |
| Service/Power Release | 11/27/2023 | Approved | WILLIAM WREN |