5223 N LAUREL CANYON BLVD 91607
Certificate Information: 5223 N LAUREL CANYON BLVD 91607
- Application / Permit
- 22016-20000-38008
- Plan Check / Job No.
- B22VN18395
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (4) Gymnasium
- Work Description
- TENANT IMPROVEMENT AND CHANGE OF USE FROM RETAIL AND MEDICAL OFFICE TO GYM
- Permit Issued
- Issued on 3/20/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2022 | SELLA BENYAMIN |
| Corrections Issued | 1/4/2023 | SELLA BENYAMIN |
| Quality Review Completed | 1/6/2023 | STEVEN KIM |
| Building Plans Picked Up | 1/10/2023 | APPLICANT |
| Plan Check Approved | 3/3/2023 | SELLA BENYAMIN |
| Issued | 3/20/2023 | APPLICANT |
| CofO in Progress | 11/21/2023 | ROBERT DAVIS |
| Permit Finaled | 11/22/2023 | JEFFREY DURAN |
| CofO Issued | 11/22/2023 | JEFFREY DURAN |
| Permit Finaled | 11/22/2023 | JEFFREY DURAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/10/2023 | CARLOS AGUILERA |
| "Q" conditions | Cleared | 1/11/2023 | NELSON RODRIGUEZ |
| Specific Plan | Cleared | 1/12/2023 | JOANNA MARROQUIN |
| DAS Clearance | Cleared | 2/17/2023 | SELLA BENYAMIN |
Contact Information
| Contractor | Floor Appeal Inc; Lic. No.: 996734-B | 22287 MULHOLLAND HWY #254 CALABASAS, CA 91302 |
| Engineer | Sabzehzar,, Habib; Lic. No.: C50442 | 8180 N PRICE AVE FRESNO, CA 93720 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/18/2023 | Corrections Issued | ROBERT DAVIS |
| Wood Frame | 4/18/2023 | Not Ready for Inspection | ROBERT DAVIS |
| Reinforced Concrete Frame | 4/28/2023 | Approved | ROBERT DAVIS |
| Wood Frame | 4/28/2023 | Partial Approval | ROBERT DAVIS |
| Drywall Nailing | 6/1/2023 | Approved | ROBERT DAVIS |
| Interior/Exterior Lathing | 6/1/2023 | Partial Approval | ROBERT DAVIS |
| Interior/Exterior Lathing | 6/12/2023 | Partial Inspection | ROBERT DAVIS |
| Final | 7/21/2023 | Not Ready for Inspection | ROBERT DAVIS |
| Reinforced Masonry Frame | 7/21/2023 | Approved | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 7/21/2023 | SGSOV No Gas | ROBERT DAVIS |
| Smoke Detectors | 7/21/2023 | Approved | ROBERT DAVIS |
| Final | 11/21/2023 | OK to Issue CofO | ROBERT DAVIS |