1002 W CHILDS WAY 90089
Certificate Information: 1002 W CHILDS WAY 90089
- Application / Permit
- 22016-20000-37645
- Plan Check / Job No.
- B22VN18214
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (18) School Building
- Work Description
- ePlan RENOVATION AT (E) LABORATORY AT 1ST FLOOR, NORTH LAB SPACE ONLY..
- Permit Issued
- Issued on 5/15/2023
- Issuing Office
- Current Status
- Permit Finaled on 8/21/2024
Permit Application Status History
| Submitted | 12/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2022 | RAPHAEL ROSAS |
| Corrections Issued | 1/6/2023 | RAPHAEL ROSAS |
| Quality Review Completed | 1/23/2023 | STEVEN KIM |
| Applicant returned to address corrections | 3/8/2023 | RAPHAEL ROSAS |
| Plan Check Approved | 5/2/2023 | RAPHAEL ROSAS |
| Issued | 5/15/2023 | APPLICANT |
| Permit Finaled | 7/23/2024 | ALFREDO LOPEZ |
Permit Application Clearance Information
| ZA Case | Cleared | 1/23/2023 | RAFAEL FONTES |
| Redevelopment Project Area | Cleared | 1/26/2023 | DAVID URITA |
| ZI | Cleared | 1/26/2023 | DAVID URITA |
| Green Code | Cleared | 2/28/2023 | MICHAEL AYERS |
| DAS Clearance | Cleared | 4/27/2023 | Hernan Arreola |
Contact Information
| Architect | Keith,, David W; Lic. No.: C39132 | 6014 PASEO ALAMEDA CARLSBAD, CA 92009 |
| Contractor | Olsen H C Construction Company Inc; Lic. No.: 177029-A | 710 E LOS ANGELES ST MONROVIA, CA 91016 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/13/2023 | Approved | ALAN MORELOS |
| Drywall Nailing | 11/8/2023 | Partial Approval | LUIS CCAMACHO |
| Light Gage Steel Frame | 11/8/2023 | Partial Approval | LUIS CCAMACHO |
| Deputy Drilled-In Anchors | 12/27/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Drywall Nailing | 3/26/2024 | Partial Approval | ALFREDO LOPEZ |
| T-Bar Ceiling | 4/11/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| T-Bar Ceiling | 4/17/2024 | Approved | ALFREDO LOPEZ |
| Final | 7/2/2024 | Conditional Approval | ALFREDO LOPEZ |
| Green Building Final | 7/2/2024 | Approved | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 7/2/2024 | SGSOV Approved | ALFREDO LOPEZ |
| Smoke Detectors | 7/2/2024 | Approved | ALFREDO LOPEZ |
| Final | 7/23/2024 | Permit Finaled | ALFREDO LOPEZ |