20065 W RINALDI ST 110 91326

Certificate Information: 20065 W RINALDI ST 110 91326

Application / Permit
22016-20000-37468
Plan Check / Job No.
B22VN18160
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
eplan: Tenant improvement to a restaurant with outdoor covered patio, nfpa-13 fire sprinklers throughout, all work per engineering
Permit Issued
Issued on 5/9/2023
Issuing Office
Current Status
CofO Issued on 12/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2022 APPLICANT
Assigned to Plan Check Engineer 12/22/2022 RARES BODEA
Corrections Issued 12/27/2022 RARES BODEA
Quality Review Completed 12/27/2022 STEVEN KIM
Applicant returned to address corrections 2/23/2023 RARES BODEA
Applicant returned to address corrections 3/3/2023 RARES BODEA
Applicant returned to address corrections 4/4/2023 RARES BODEA
Plan Check Approved 4/25/2023 RARES BODEA
Issued 5/9/2023 APPLICANT
CofO in Progress 12/1/2023 DEANDRE HOFFMAN
Permit Finaled 12/4/2023 JEFFREY DURAN
CofO Issued 12/4/2023 JEFFREY DURAN
Permit Finaled 12/4/2023 JEFFREY DURAN

Permit Application Clearance Information

Specific Plan Cleared 1/5/2023 SHEILA AHORAIAN
Address approval Cleared 1/6/2023 CARLOS AGUILERA
"D" conditions Cleared 1/10/2023 DANG NGUYEN
"T" removal Cleared 1/10/2023 DANG NGUYEN
CPC Cleared 1/10/2023 DANG NGUYEN
Miscellaneous Cleared 1/10/2023 DANG NGUYEN
Miscellaneous Cleared 1/10/2023 DANG NGUYEN
Miscellaneous Cleared 1/10/2023 DANG NGUYEN
Miscellaneous Cleared 1/10/2023 DANG NGUYEN
Miscellaneous Cleared 1/10/2023 DANG NGUYEN
Miscellaneous Cleared 1/10/2023 DANG NGUYEN
Miscellaneous Cleared 1/10/2023 DANG NGUYEN
Miscellaneous Cleared 1/10/2023 DANG NGUYEN
Miscellaneous Cleared 1/10/2023 DANG NGUYEN
Miscellaneous Cleared 1/10/2023 DANG NGUYEN
Miscellaneous Cleared 1/10/2023 DANG NGUYEN
Miscellaneous Cleared 1/10/2023 DANG NGUYEN
Miscellaneous Cleared 1/10/2023 DANG NGUYEN
Miscellaneous Cleared 1/10/2023 DANG NGUYEN
Tract Map conditions Cleared 1/10/2023 DANG NGUYEN
Tract Map conditions Cleared 1/10/2023 DANG NGUYEN
Tract Map conditions Cleared 1/10/2023 DANG NGUYEN
ZA Case Cleared 1/10/2023 DANG NGUYEN
Eng Process Fee Ord 176,300 Cleared 2/15/2023 CARLOS AGUILERA
Sewer availability Cleared 2/15/2023 CARLOS AGUILERA
DAS Clearance Cleared 2/17/2023 Joe Vo
Green Code Cleared 3/7/2023 MICHAEL AYERS
Food Service Establishment Cleared 3/16/2023 PAWAN VERMA
Specific Plan Cleared 3/24/2023 CLAUDIA RODRIGUEZ
ZI Cleared 3/24/2023 CLAUDIA RODRIGUEZ
Food establishment approval Cleared 4/4/2023 LACDHS APPROVED
Fire Marshall Fire Life Safety Cleared 4/13/2023 SARAH ZHANG
CPC Cleared 4/24/2023 DANG NGUYEN

Contact Information

Architect Rachel, Turner Lauck; Lic. No.: C40063       ,
Contractor P9 Construction Company; Lic. No.: 1071823-B       ,
Engineer Young,, Bradley Rae; Lic. No.: S4727 345 POLLASKY AVENUE      CLOVIS, CA 93612

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/10/2023 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 6/12/2023 Conditional Approval DEANDRE HOFFMAN
Light Gage Steel Frame 6/30/2023 Partial Inspection DEANDRE HOFFMAN
Drywall Nailing 7/13/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 7/13/2023 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 7/20/2023 Partial Inspection DEANDRE HOFFMAN
Green Building Rough 7/20/2023 Approved DEANDRE HOFFMAN
Light Gage Steel Frame 9/7/2023 Partial Inspection JEFFREY FULTON
T-Bar Ceiling 9/22/2023 Corrections Issued DEANDRE HOFFMAN
T-Bar Ceiling 9/28/2023 Partial Inspection DEANDRE HOFFMAN
Drywall Nailing 11/16/2023 Not Ready for Inspection ANDREW DORSO
Final 11/16/2023 Partial Inspection ANDREW DORSO
Green Building Final 11/16/2023 Not Ready for Inspection ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 11/16/2023 SGSOV Not Ready ANDREW DORSO
Smoke Detectors 11/16/2023 Not Ready for Inspection ANDREW DORSO
Verify Sprinkler Sign Off 11/16/2023 Not Ready for Inspection ANDREW DORSO
Wood Frame 11/16/2023 Not Ready for Inspection ANDREW DORSO
Drywall Nailing 11/22/2023 Not Ready for Inspection CAMERON CHABAN
Final 11/22/2023 Not Ready for Inspection CAMERON CHABAN
Green Building Final 11/22/2023 Not Ready for Inspection CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 11/22/2023 SGSOV Not Ready CAMERON CHABAN
Smoke Detectors 11/22/2023 Not Ready for Inspection CAMERON CHABAN
Verify Sprinkler Sign Off 11/22/2023 Not Ready for Inspection CAMERON CHABAN
Wood Frame 11/22/2023 Not Ready for Inspection CAMERON CHABAN
Drywall Nailing 11/27/2023 Approved DEANDRE HOFFMAN
Final 11/27/2023 Partial Inspection DEANDRE HOFFMAN
Green Building Final 11/27/2023 Approved DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 11/27/2023 SGSOV Approved DEANDRE HOFFMAN
Smoke Detectors 11/27/2023 Approved DEANDRE HOFFMAN
Verify Sprinkler Sign Off 11/27/2023 Approved DEANDRE HOFFMAN
Wood Frame 11/27/2023 Approved DEANDRE HOFFMAN
Special/Order Compliance 11/28/2023 Not Ready for Inspection DEANDRE HOFFMAN
Final 11/30/2023 OK to Issue CofO DEANDRE HOFFMAN