20065 W RINALDI ST 110 91326
Certificate Information: 20065 W RINALDI ST 110 91326
- Application / Permit
- 22016-20000-37468
- Plan Check / Job No.
- B22VN18160
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- eplan: Tenant improvement to a restaurant with outdoor covered patio, nfpa-13 fire sprinklers throughout, all work per engineering
- Permit Issued
- Issued on 5/9/2023
- Issuing Office
- Current Status
- CofO Issued on 12/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2022 | RARES BODEA |
| Corrections Issued | 12/27/2022 | RARES BODEA |
| Quality Review Completed | 12/27/2022 | STEVEN KIM |
| Applicant returned to address corrections | 2/23/2023 | RARES BODEA |
| Applicant returned to address corrections | 3/3/2023 | RARES BODEA |
| Applicant returned to address corrections | 4/4/2023 | RARES BODEA |
| Plan Check Approved | 4/25/2023 | RARES BODEA |
| Issued | 5/9/2023 | APPLICANT |
| CofO in Progress | 12/1/2023 | DEANDRE HOFFMAN |
| Permit Finaled | 12/4/2023 | JEFFREY DURAN |
| CofO Issued | 12/4/2023 | JEFFREY DURAN |
| Permit Finaled | 12/4/2023 | JEFFREY DURAN |
Permit Application Clearance Information
| Specific Plan | Cleared | 1/5/2023 | SHEILA AHORAIAN |
| Address approval | Cleared | 1/6/2023 | CARLOS AGUILERA |
| "D" conditions | Cleared | 1/10/2023 | DANG NGUYEN |
| "T" removal | Cleared | 1/10/2023 | DANG NGUYEN |
| CPC | Cleared | 1/10/2023 | DANG NGUYEN |
| Miscellaneous | Cleared | 1/10/2023 | DANG NGUYEN |
| Miscellaneous | Cleared | 1/10/2023 | DANG NGUYEN |
| Miscellaneous | Cleared | 1/10/2023 | DANG NGUYEN |
| Miscellaneous | Cleared | 1/10/2023 | DANG NGUYEN |
| Miscellaneous | Cleared | 1/10/2023 | DANG NGUYEN |
| Miscellaneous | Cleared | 1/10/2023 | DANG NGUYEN |
| Miscellaneous | Cleared | 1/10/2023 | DANG NGUYEN |
| Miscellaneous | Cleared | 1/10/2023 | DANG NGUYEN |
| Miscellaneous | Cleared | 1/10/2023 | DANG NGUYEN |
| Miscellaneous | Cleared | 1/10/2023 | DANG NGUYEN |
| Miscellaneous | Cleared | 1/10/2023 | DANG NGUYEN |
| Miscellaneous | Cleared | 1/10/2023 | DANG NGUYEN |
| Miscellaneous | Cleared | 1/10/2023 | DANG NGUYEN |
| Miscellaneous | Cleared | 1/10/2023 | DANG NGUYEN |
| Tract Map conditions | Cleared | 1/10/2023 | DANG NGUYEN |
| Tract Map conditions | Cleared | 1/10/2023 | DANG NGUYEN |
| Tract Map conditions | Cleared | 1/10/2023 | DANG NGUYEN |
| ZA Case | Cleared | 1/10/2023 | DANG NGUYEN |
| Eng Process Fee Ord 176,300 | Cleared | 2/15/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/15/2023 | CARLOS AGUILERA |
| DAS Clearance | Cleared | 2/17/2023 | Joe Vo |
| Green Code | Cleared | 3/7/2023 | MICHAEL AYERS |
| Food Service Establishment | Cleared | 3/16/2023 | PAWAN VERMA |
| Specific Plan | Cleared | 3/24/2023 | CLAUDIA RODRIGUEZ |
| ZI | Cleared | 3/24/2023 | CLAUDIA RODRIGUEZ |
| Food establishment approval | Cleared | 4/4/2023 | LACDHS APPROVED |
| Fire Marshall Fire Life Safety | Cleared | 4/13/2023 | SARAH ZHANG |
| CPC | Cleared | 4/24/2023 | DANG NGUYEN |
Contact Information
| Architect | Rachel, Turner Lauck; Lic. No.: C40063 | , |
| Contractor | P9 Construction Company; Lic. No.: 1071823-B | , |
| Engineer | Young,, Bradley Rae; Lic. No.: S4727 | 345 POLLASKY AVENUE CLOVIS, CA 93612 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/10/2023 | Conditional Approval | CAMERON CHABAN |
| Deputy Reinf. Concrete | 6/12/2023 | Conditional Approval | DEANDRE HOFFMAN |
| Light Gage Steel Frame | 6/30/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Drywall Nailing | 7/13/2023 | Partial Inspection | JEFFREY FULTON |
| Green Building Rough | 7/13/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Drywall Nailing | 7/20/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Green Building Rough | 7/20/2023 | Approved | DEANDRE HOFFMAN |
| Light Gage Steel Frame | 9/7/2023 | Partial Inspection | JEFFREY FULTON |
| T-Bar Ceiling | 9/22/2023 | Corrections Issued | DEANDRE HOFFMAN |
| T-Bar Ceiling | 9/28/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Drywall Nailing | 11/16/2023 | Not Ready for Inspection | ANDREW DORSO |
| Final | 11/16/2023 | Partial Inspection | ANDREW DORSO |
| Green Building Final | 11/16/2023 | Not Ready for Inspection | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 11/16/2023 | SGSOV Not Ready | ANDREW DORSO |
| Smoke Detectors | 11/16/2023 | Not Ready for Inspection | ANDREW DORSO |
| Verify Sprinkler Sign Off | 11/16/2023 | Not Ready for Inspection | ANDREW DORSO |
| Wood Frame | 11/16/2023 | Not Ready for Inspection | ANDREW DORSO |
| Drywall Nailing | 11/22/2023 | Not Ready for Inspection | CAMERON CHABAN |
| Final | 11/22/2023 | Not Ready for Inspection | CAMERON CHABAN |
| Green Building Final | 11/22/2023 | Not Ready for Inspection | CAMERON CHABAN |
| SGSOV-Seismic Gas S/O Valve | 11/22/2023 | SGSOV Not Ready | CAMERON CHABAN |
| Smoke Detectors | 11/22/2023 | Not Ready for Inspection | CAMERON CHABAN |
| Verify Sprinkler Sign Off | 11/22/2023 | Not Ready for Inspection | CAMERON CHABAN |
| Wood Frame | 11/22/2023 | Not Ready for Inspection | CAMERON CHABAN |
| Drywall Nailing | 11/27/2023 | Approved | DEANDRE HOFFMAN |
| Final | 11/27/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Green Building Final | 11/27/2023 | Approved | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 11/27/2023 | SGSOV Approved | DEANDRE HOFFMAN |
| Smoke Detectors | 11/27/2023 | Approved | DEANDRE HOFFMAN |
| Verify Sprinkler Sign Off | 11/27/2023 | Approved | DEANDRE HOFFMAN |
| Wood Frame | 11/27/2023 | Approved | DEANDRE HOFFMAN |
| Special/Order Compliance | 11/28/2023 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Final | 11/30/2023 | OK to Issue CofO | DEANDRE HOFFMAN |