8214 N RHODES AVE 91605
Certificate Information: 8214 N RHODES AVE 91605
- Application / Permit
- 22016-20000-37342
- Plan Check / Job No.
- B22VN18130
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (E) GARAGE AND STORAGE CONVERSION TO ONE STORY DETACHED ADU PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 2/3/2023
- Issuing Office
- Current Status
- CofO Issued on 5/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/9/2022 | APPLICANT |
| Corrections Issued | 12/12/2022 | JESSE ARELLANO |
| Assigned to Plan Check Engineer | 12/13/2022 | JESSE ARELLANO |
| Building Plans Picked Up | 12/19/2022 | APPLICANT |
| Plan Check Approved | 2/2/2023 | RAMA DABADGE |
| Issued | 2/3/2023 | APPLICANT |
| CofO in Progress | 5/1/2024 | MATTHEW NELSON |
| Permit Finaled | 5/2/2024 | RUBEN SALAS |
| CofO Issued | 5/2/2024 | RUBEN SALAS |
| Permit Finaled | 5/2/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/3/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 1/3/2023 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/13/2023 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 3/21/2023 | Partial Inspection | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 4/6/2023 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 4/28/2023 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/3/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Rough | 8/3/2023 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 9/1/2023 | Partial Inspection | DAVID MATSON |
| ELECTRICAL-Rough | 9/1/2023 | Corrections Issued | DAVID MATSON |
| Green Building Rough | 9/1/2023 | Approved | DAVID MATSON |
| HVAC-Rough | 9/1/2023 | Not Ready for Inspection | DAVID MATSON |
| PLUMBING-Rough | 9/1/2023 | Not Ready for Inspection | DAVID MATSON |
| Rough-Elec/Plmb/HVAC | 9/12/2023 | No Access for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 9/14/2023 | Approved | WILLIAM WREN |
| HVAC-Rough | 9/14/2023 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 9/14/2023 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 9/15/2023 | Approved | WILLIAM WREN |
| HVAC-Rough | 9/15/2023 | Approved | WILLIAM WREN |
| Insulation | 9/20/2023 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2023 | Approved | WILLIAM WREN |
| Drywall Nailing | 10/3/2023 | Approved | WILLIAM WREN |
| Shower Pan | 10/3/2023 | Approved | WILLIAM WREN |
| Rough-Elec/Plmb/HVAC | 2/23/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 4/24/2024 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 4/24/2024 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 4/24/2024 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 4/24/2024 | Approved | MATTHEW NELSON |
| Final | 4/30/2024 | OK to Issue CofO | MATTHEW NELSON |
| Service/Power Release | 5/1/2024 | Approved | MATTHEW NELSON |