7858-7860 N TROOST AVE 91605
Certificate Information: 7858-7860 N TROOST AVE 91605
- Application / Permit
- 22016-20000-37108
- Plan Check / Job No.
- B22VN18001
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- **Eplan** Convert (e) attached garage to junior accessory dwelling unit per state law (CAGC 65852.2(e)(1)(A) and 65852.22) . Construction per engineered design. **NFPA 13D FIRE SPRINKLERS THROUGHOUT**
- Permit Issued
- Issued on 2/27/2023
- Issuing Office
- Current Status
- CofO Issued on 10/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2022 | GEORGE ALVAREZ |
| Corrections Issued | 12/21/2022 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 1/17/2023 | ADAM HEGAZI |
| Plan Check Approved | 2/21/2023 | GEORGE ALVAREZ |
| Issued | 2/27/2023 | APPLICANT |
| CofO in Progress | 9/20/2023 | DAVID ANDERSON |
| CofO in Progress | 10/5/2023 | DAVID ANDERSON |
| CofO in Progress | 10/5/2023 | DAVID ANDERSON |
| CofO in Progress | 10/5/2023 | DAVID ANDERSON |
| CofO Issued | 10/5/2023 | RUBEN SALAS |
| Permit Finaled | 10/5/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/22/2022 | RYAN KIM |
| Sewer availability | Cleared | 12/22/2022 | RYAN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 2/2/2023 | ROSE MARIE SMITH |
| Miscellaneous | Cleared | 2/21/2023 | GEORGE ALVAREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/21/2023 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 3/21/2023 | Partial Approval | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 3/28/2023 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 3/28/2023 | Approved | MATTHEW NELSON |
| Pre-Inspection | 3/28/2023 | Approved | MATTHEW NELSON |
| Pre-Inspection | 4/21/2023 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 5/25/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Gas Test | 5/25/2023 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 5/25/2023 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 6/1/2023 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 6/1/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Gas Test | 6/1/2023 | Approved | MATTHEW NELSON |
| Green Building Rough | 6/1/2023 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 6/1/2023 | Corrections Issued | MATTHEW NELSON |
| BUILDING-Rough-Frame | 6/2/2023 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 6/2/2023 | Approved | MATTHEW NELSON |
| HVAC-Rough | 6/2/2023 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 6/2/2023 | Approved | MATTHEW NELSON |
| Insulation | 6/7/2023 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 6/7/2023 | Approved | MATTHEW NELSON |
| Shower Pan | 6/7/2023 | Approved | MATTHEW NELSON |
| Drywall Nailing | 6/14/2023 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 6/14/2023 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 8/3/2023 | SGSOV Not Ready | MATTHEW NELSON |
| ELECTRICAL-Final | 8/10/2023 | Corrections Issued | MATTHEW NELSON |
| HVAC-Final | 8/10/2023 | Corrections Issued | MATTHEW NELSON |
| MERV13>=Final | 8/10/2023 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 8/10/2023 | Conditional Approval | MATTHEW NELSON |
| Final | 8/15/2023 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 8/15/2023 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 8/15/2023 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 8/15/2023 | Approved | MATTHEW NELSON |
| Final | 8/25/2023 | Conditional Approval | DAVID ANDERSON |
| Green Building Final | 8/25/2023 | Approved | DAVID ANDERSON |
| Final | 9/20/2023 | OK to Issue CofO | DAVID ANDERSON |