Work Description
Eplan Scope of work shall include partial removal and demolition of existing walls, doors, and ceiling along with the addition of new plumbing fixtures on level b01. scope also includes new carpet, paint and wall-applied finishes and base along with new light fixtures on level 01. (No exterior work)
Permit Issued
Issued on 6/15/2023
Issuing Office
Current Status
Permit Finaled on 6/24/2025

Permit Application Status History

Submitted 12/22/2022 APPLICANT
Assigned to Plan Check Engineer 1/27/2023 HANS SANTIAGO
Corrections Issued 1/30/2023 HANS SANTIAGO
Quality Review Completed 2/2/2023 LIPING TENG
Plan Check Approved 6/8/2023 ANDREW SANTIAGO
Issued 6/15/2023 APPLICANT
Permit Finaled 6/24/2025 PAUL BAZERKANIAN

Permit Application Clearance Information

Green Code Cleared 5/4/2023 MICHAEL AYERS
DAS Clearance Cleared 5/19/2023 Samuel Gonzalez

Contact Information

Architect Wicksman,, Warwick Ian; Lic. No.: C23350 22844 DOLOROSA ST      WOODLAND HILLS, CA 91367
Contractor Taslimi Construction Co Inc; Lic. No.: 475159-B       ,

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/26/2023 Partial Inspection RAMAZANALI ALMASI
Light Gage Steel Frame 11/8/2023 Partial Inspection KATY RAMIREZ
Insulation 11/13/2023 Corrections Issued KATY RAMIREZ
Light Gage Steel Frame 11/21/2023 Partial Inspection KATY RAMIREZ
Drywall Nailing 11/28/2023 Partial Approval JEROME BLACKWOOD
Light Gage Steel Frame 1/17/2024 Partial Inspection KATY RAMIREZ
Drywall Nailing 1/23/2024 Partial Approval JEROME BLACKWOOD
Light Gage Steel Frame 4/3/2024 Partial Approval JEROME BLACKWOOD
Drywall Nailing 4/8/2024 Partial Approval TIMOTHY POWELL
Light Gage Steel Frame 5/2/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 5/6/2024 Partial Approval LUIS CCAMACHO
Pre-Inspection 5/10/2024 Not Ready for Inspection LUIS CCAMACHO
Light Gage Steel Frame 5/16/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 5/20/2024 Partial Approval JACOB MYERS
Light Gage Steel Frame 9/12/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 9/16/2024 Partial Approval PAUL BAZERKANIAN
Pre-Inspection 6/3/2025 Not Ready for Inspection JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 6/6/2025 SGSOV Approved PAUL BAZERKANIAN
Final 6/17/2025 Not Ready for Inspection JEROME BLACKWOOD
Green Building Final 6/17/2025 Not Ready for Inspection JEROME BLACKWOOD
Smoke Detectors 6/17/2025 Approved JEROME BLACKWOOD
Final 6/24/2025 Permit Finaled PAUL BAZERKANIAN
Green Building Final 6/24/2025 Approved PAUL BAZERKANIAN