14530 W SYLVAN ST 91411

Certificate Information: 14530 W SYLVAN ST 91411

Application / Permit
22016-20000-37017
Plan Check / Job No.
B22VN17961
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Physical Culture Institution
Work Description
TENANT IMPROVEMENT TO (E) PHYSICAL CULTURE INSTITUTION: ADD/DEMOLISH NON-BEARING PARTITIONS
Permit Issued
Issued on 6/19/2023
Issuing Office
Current Status
Permit Finaled on 3/29/2024

Permit Application Status History

Submitted 12/8/2022 APPLICANT
Assigned to Plan Check Engineer 12/22/2022 NILOOFAR MEHRAIN
Corrections Issued 12/27/2022 NILOOFAR MEHRAIN
Quality Review Completed 12/28/2022 STEVEN KIM
Applicant returned to address corrections 3/15/2023 NILOOFAR MEHRAIN
Applicant returned to address corrections 3/22/2023 NILOOFAR MEHRAIN
Applicant returned to address corrections 4/26/2023 NILOOFAR MEHRAIN
Plan Check Approved 6/14/2023 NILOOFAR MEHRAIN
Issued 6/19/2023 APPLICANT
Permit Finaled 3/29/2024 BRIAN KELLY

Permit Application Clearance Information

"Q" conditions Cleared 1/23/2023 NOAH MCCOY
CPC Cleared 1/23/2023 NOAH MCCOY
Supp. Use District POD/CDO/TDO Cleared 1/23/2023 NOAH MCCOY
ZI Cleared 1/23/2023 NOAH MCCOY
Green Code Cleared 3/9/2023 MICHAEL AYERS
Fire Marshal Fire Life Safety Cleared 3/14/2023 MENOA AGHAJANI
Sewer availability Cleared 3/15/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 3/22/2023 DAGOVERTO GUERRERO
DAS Clearance Cleared 5/3/2023 NILOOFAR MEHRAIN

Contact Information

Contractor Mfi Construction Inc; Lic. No.: 902456-B       ,

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/5/2023 Conditional Approval BRIAN KELLY
Insulation 7/20/2023 Not Ready for Inspection JEFFREY FULTON
Pre-Inspection 7/20/2023 Partial Inspection JEFFREY FULTON
Wood Frame 7/20/2023 Partial Inspection JEFFREY FULTON
Pre-Inspection 8/17/2023 Partial Approval BRIAN KELLY
Special/Order Compliance 8/17/2023 Partial Inspection JEFFREY FULTON
Pre-Inspection 8/23/2023 Partial Inspection ANDREW DORSO
Pre-Inspection 8/24/2023 Partial Inspection ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 10/6/2023 Approved ANDREW DORSO
Wood Frame 10/6/2023 Partial Inspection ANDREW DORSO
Drywall Nailing 10/11/2023 Partial Approval KENNETH ROBERTS
Insulation 10/11/2023 Approved KENNETH ROBERTS
Drywall Nailing 10/13/2023 Partial Approval STEVEN LEVITT
T-Bar Ceiling 10/24/2023 Partial Inspection BRIAN KELLY
Insulation 10/27/2023 Partial Approval DEANDRE HOFFMAN
Drywall Nailing 10/31/2023 Partial Approval STEVEN LEVITT
Light Gage Steel Frame 11/9/2023 Partial Inspection ANDREW DORSO
Special/Order Compliance 11/9/2023 Partial Inspection ANDREW DORSO
Insulation 11/15/2023 Partial Inspection ANDREW DORSO
Drywall Nailing 11/20/2023 Partial Inspection ANDREW DORSO
Special/Order Compliance 11/20/2023 Not Ready for Inspection ANDREW DORSO
Special/Order Compliance 11/22/2023 Partial Approval STEVEN LEVITT
Special/Order Compliance 12/6/2023 Partial Inspection BRIAN KELLY
Drywall Nailing 12/8/2023 Partial Approval STEVEN LEVITT
Special/Order Compliance 12/29/2023 Partial Approval JEFFREY DURAN
Special/Order Compliance 12/29/2023 Partial Inspection BRIAN KELLY
T-Bar Ceiling 1/18/2024 Partial Approval BRIAN KELLY
Special/Order Compliance 1/25/2024 Partial Inspection JEFFREY DURAN
T-Bar Ceiling 1/25/2024 Partial Inspection BRIAN KELLY
Special/Order Compliance 1/30/2024 Partial Inspection BRIAN KELLY
T-Bar Ceiling 2/8/2024 Approved BRIAN KELLY
Excavation/Setback/Form/Re-Bar 2/12/2024 Partial Approval BRIAN KELLY
Drywall Nailing 2/21/2024 Partial Approval BRIAN KELLY
Excavation/Setback/Form/Re-Bar 2/21/2024 Partial Inspection BRIAN KELLY
Special/Order Compliance 3/12/2024 Partial Inspection BRIAN KELLY
Final 3/21/2024 Not Ready for Inspection BRIAN KELLY
Green Building Final 3/21/2024 Not Ready for Inspection BRIAN KELLY
SGSOV-Seismic Gas S/O Valve 3/21/2024 SGSOV Not Ready BRIAN KELLY
Smoke Detectors 3/21/2024 Not Ready for Inspection BRIAN KELLY
Special/Order Compliance 3/26/2024 Partial Inspection BRIAN KELLY
Final 3/27/2024 Not Ready for Inspection BRIAN KELLY
Green Building Final 3/27/2024 Not Ready for Inspection BRIAN KELLY
SGSOV-Seismic Gas S/O Valve 3/27/2024 SGSOV Not Ready BRIAN KELLY
Smoke Detectors 3/27/2024 Not Ready for Inspection BRIAN KELLY
Final 3/28/2024 Not Ready for Inspection BRIAN KELLY
Green Building Final 3/28/2024 Not Ready for Inspection BRIAN KELLY
SGSOV-Seismic Gas S/O Valve 3/28/2024 SGSOV Not Ready BRIAN KELLY
Smoke Detectors 3/28/2024 Not Ready for Inspection BRIAN KELLY
Final 3/29/2024 Permit Finaled BRIAN KELLY
Green Building Final 3/29/2024 Approved BRIAN KELLY
SGSOV-Seismic Gas S/O Valve 3/29/2024 SGSOV Approved BRIAN KELLY
Smoke Detectors 3/29/2024 Approved BRIAN KELLY