20957 W MARMORA ST 91364

Certificate Information: 20957 W MARMORA ST 91364

Application / Permit
22016-20000-36917
Plan Check / Job No.
B22VN17919
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* CONVERT (E) DETACHED 2-CAR GARAGE TO ADU PER CA 65852.2(e)(1)(A).
Permit Issued
Issued on 12/7/2023
Issuing Office
Current Status
CofO in Progress on 12/16/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/8/2022 APPLICANT
Assigned to Plan Check Engineer 12/15/2022 VIVIAN LAO
Corrections Issued 12/16/2022 VIVIAN LAO
Applicant returned to address corrections 7/12/2023 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 7/25/2023 FARSHAD ALIMOHAMADI
Plan Check Approved 8/24/2023 FARSHAD ALIMOHAMADI
Issued 12/7/2023 APPLICANT
CofO in Progress 12/16/2025 SEAN WIRCH

Permit Application Clearance Information

Address approval Cleared 1/5/2023 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 1/5/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 1/5/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 1/10/2023 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 1/30/2023 KIRK LINKLATER
Specific Plan Cleared 5/25/2023 OLGA AYALA
Specific Plan Cleared 5/25/2023 OLGA AYALA

Contact Information

Contractor Owner-Builder       ,
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/24/2024 Not Ready for Inspection KRISTEN CAUSEY
HVAC-Final 1/24/2024 Not Ready for Inspection KRISTEN CAUSEY
HVAC-Rough 1/24/2024 Not Ready for Inspection KRISTEN CAUSEY
PLUMBING-Rough 1/24/2024 Not Ready for Inspection KRISTEN CAUSEY
Wood Frame 1/24/2024 Not Ready for Inspection KRISTEN CAUSEY
BUILDING-Rough-Frame 2/20/2024 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 2/20/2024 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 2/20/2024 Partial Approval JOHN KIDWELL
Green Building Rough 2/20/2024 Not Ready for Inspection JOHN KIDWELL
HVAC-Rough 2/20/2024 Approved JOHN KIDWELL
PLUMBING-Rough 2/20/2024 Approved JOHN KIDWELL
BUILDING-Rough-Frame 3/8/2024 Not Ready for Inspection MORRIS JACKSON
Footing/Foundation/Slab 3/8/2024 Not Ready for Inspection MORRIS JACKSON
Green Building Rough 3/8/2024 Not Ready for Inspection MORRIS JACKSON
Insulation 3/8/2024 Approved MORRIS JACKSON
Interior/Exterior Lathing 3/8/2024 Not Ready for Inspection MORRIS JACKSON
BUILDING-Rough-Frame 3/22/2024 Approved JOHN KIDWELL
Drywall Nailing 3/22/2024 Approved JOHN KIDWELL
Green Building Rough 3/22/2024 Approved JOHN KIDWELL
Interior/Exterior Lathing 3/22/2024 Approved JOHN KIDWELL
Shower Pan 3/22/2024 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 5/17/2024 SGSOV Not Ready JOHN HAYES
Final 5/20/2024 Corrections Issued JOHN HAYES
Green Building Final 5/20/2024 Not Ready for Inspection JOHN HAYES
Pre-Inspection 5/20/2024 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 5/20/2024 SGSOV Not Ready JOHN HAYES
Smoke Detectors 5/20/2024 Not Ready for Inspection JOHN HAYES
Final 6/5/2024 No Access for Inspection JOHN HAYES
Green Building Final 6/5/2024 No Access for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 6/5/2024 SGSOV Not Ready JOHN HAYES
Smoke Detectors 6/5/2024 No Access for Inspection JOHN HAYES
Final 6/12/2024 Corrections Issued JOHN HAYES
Green Building Final 6/12/2024 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 6/12/2024 SGSOV Not Ready JOHN HAYES
Smoke Detectors 6/12/2024 Not Ready for Inspection JOHN HAYES
Final 6/13/2024 Corrections Issued JOHN HAYES
Green Building Final 6/13/2024 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 6/13/2024 SGSOV Not Ready JOHN HAYES
Smoke Detectors 6/13/2024 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 6/18/2024 Corrections Issued HENRY KIM
PLUMBING-Final 6/18/2024 Corrections Issued HENRY KIM
Special/Order Compliance 6/18/2024 Approved HENRY KIM
Special/Order Compliance 6/18/2024 Partial Inspection SEAN WIRCH
Underground Mechanical 6/18/2024 Corrections Issued HENRY KIM
Final 7/23/2024 Not Ready for Inspection JOHN HAYES
Green Building Final 7/23/2024 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 7/23/2024 SGSOV Not Ready JOHN HAYES
Service/Power Release 7/23/2024 Not Ready for Inspection JOHN HAYES
Smoke Detectors 7/23/2024 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 8/6/2024 SGSOV Not Ready JOHN HAYES
Final 12/16/2025 OK to Issue CofO SEAN WIRCH
Green Building Final 12/16/2025 Approved SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 12/16/2025 SGSOV Approved SEAN WIRCH
Smoke Detectors 12/16/2025 Approved SEAN WIRCH