7115-7117 N COSTELLO AVE 91405

Certificate Information: 7115-7117 N COSTELLO AVE 91405

Application / Permit
22016-20000-36914
Plan Check / Job No.
B22VN17914
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert existing attached garage into JADU per GCS 65852.2(e)(1)(A) and 65852.22
Permit Issued
Issued on 12/15/2022
Issuing Office
Valley
Current Status
CofO Issued on 7/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/6/2022 APPLICANT
Assigned to Plan Check Engineer 12/8/2022 RAMA DABADGE
Corrections Issued 12/12/2022 RAMA DABADGE
Building Plans Picked Up 12/14/2022 APPLICANT
Plan Check Approved 12/15/2022 OMAR GARNICA
Issued 12/15/2022 APPLICANT
CofO in Progress 7/19/2023 ROBERT GOLD
Permit Finaled 7/24/2023 DANIEL ORRANTE
CofO Issued 7/24/2023 DANIEL ORRANTE
Permit Finaled 7/24/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/14/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 12/14/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 12/14/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 12/14/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/6/2023 Partial Approval RYAN SALAZAR
Deputy Drilled-In Anchors 3/8/2023 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 3/8/2023 Approved RYAN SALAZAR
Footing/Foundation/Slab 3/8/2023 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 3/20/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 3/29/2023 Approved RYAN SALAZAR
ELECTRICAL-Rough 3/29/2023 Approved RYAN SALAZAR
Green Building Rough 3/29/2023 Approved RYAN SALAZAR
HVAC-Rough 3/29/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 3/29/2023 Partial Approval RYAN SALAZAR
PLUMBING-Rough 3/29/2023 Approved RYAN SALAZAR
Insulation 4/4/2023 Approved RYAN SALAZAR
Shower Pan 4/4/2023 Approved RYAN SALAZAR
Drywall Nailing 4/11/2023 Approved RYAN SALAZAR
ELECTRICAL-Final 7/5/2023 Approved RYAN SALAZAR
Final 7/5/2023 Corrections Issued RYAN SALAZAR
Green Building Final 7/5/2023 Approved RYAN SALAZAR
HVAC-Final 7/5/2023 Approved RYAN SALAZAR
PLUMBING-Final 7/5/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 7/5/2023 SGSOV Approved RYAN SALAZAR
Smoke Detectors 7/5/2023 Approved RYAN SALAZAR
Final 7/19/2023 OK to Issue CofO ROBERT GOLD