4846 N RANCHITO AVE 91423

Certificate Information: 4846 N RANCHITO AVE 91423

Application / Permit
22016-20000-36863
Plan Check / Job No.
B22VN17893
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing detached garage into one story detached ADU per GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 3/21/2023
Issuing Office
Valley
Current Status
CofO Issued on 10/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/6/2022 APPLICANT
Assigned to Plan Check Engineer 12/8/2022 RAMA DABADGE
Corrections Issued 12/12/2022 RAMA DABADGE
Building Plans Picked Up 12/14/2022 APPLICANT
Plan Check Approved 3/21/2023 ALEC MOUSAKHANIAN
Issued 3/21/2023 APPLICANT
CofO in Progress 10/11/2024 MISAEL ESPARZA
CofO Issued 10/23/2024 DANIEL ORRANTE
Permit Finaled 10/23/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/30/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 1/30/2023 COLIN LOREDO
Sewer availability Cleared 1/30/2023 COLIN LOREDO
ZI Cleared 1/30/2023 STEVEN WECHSLER
Construction near power lines Cleared 3/18/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Eddy Alexander; Lic. No.: S6159 17958 LULL ST      RESEDA, CA 91335
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/12/2023 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 5/19/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 5/26/2023 Partial Approval JOHN COLEMAN
ELECTRICAL-Rough 7/7/2023 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 7/7/2023 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 7/10/2023 Corrections Issued RAUL OLAGI
Underground Mechanical 7/10/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 7/14/2023 Approved THOMAS FINNILA
PLUMBING-Rough 7/14/2023 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 7/28/2023 Approved MISAEL ESPARZA
PLUMBING-Rough 7/28/2023 Conditional Approval MISAEL ESPARZA
BUILDING-Rough-Frame 12/8/2023 Partial Approval MISAEL ESPARZA
HVAC-Rough 12/8/2023 Approved MISAEL ESPARZA
PLUMBING-Rough 12/8/2023 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 12/14/2023 Partial Approval MISAEL ESPARZA
Green Building Rough 12/14/2023 Approved MISAEL ESPARZA
Insulation 12/14/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 12/20/2023 Partial Approval MISAEL ESPARZA
Wood Frame 12/20/2023 Approved MISAEL ESPARZA
Drywall Nailing 12/22/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 1/23/2024 Approved MISAEL ESPARZA
Shower Pan 1/23/2024 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 8/28/2024 Approved MISAEL ESPARZA
Final 8/28/2024 Corrections Issued MISAEL ESPARZA
Green Building Final 8/28/2024 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 8/28/2024 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 8/28/2024 Corrections Issued MISAEL ESPARZA
Final 10/8/2024 OK to Issue CofO MISAEL ESPARZA
Green Building Final 10/8/2024 Approved MISAEL ESPARZA
Smoke Detectors 10/8/2024 Approved MISAEL ESPARZA