24343-24345 W CALVERT ST 91367
Certificate Information: 24343-24345 W CALVERT ST 91367
- Application / Permit
- 22016-20000-36773
- Plan Check / Job No.
- B22VN17853
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN convert existing attached 20x23 two-car garage to accessory dwelling unit per LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 5/30/2023
- Issuing Office
- Current Status
- CofO Issued on 2/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 1/3/2023 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 1/13/2023 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 4/7/2023 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 4/25/2023 | MOHAMMAD ESMAILI |
| Plan Check Approved | 5/22/2023 | MOHAMMAD ESMAILI |
| Issued | 5/30/2023 | APPLICANT |
| CofO in Progress | 12/20/2023 | TROY SANDERS |
| CofO Issued | 2/22/2024 | JOHN JANSON |
| Permit Finaled | 2/22/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/9/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 1/9/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 1/11/2023 | COLIN LOREDO |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/16/2023 | Conditional Approval | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 6/21/2023 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 6/29/2023 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 6/29/2023 | Approved | TROY SANDERS |
| PLUMBING-Rough | 6/29/2023 | Corrections Issued | TROY SANDERS |
| Insulation | 7/5/2023 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 7/5/2023 | Partial Approval | MORRIS JACKSON |
| Drywall Nailing | 7/13/2023 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 9/18/2023 | Approved | TROY SANDERS |
| Final | 9/18/2023 | Corrections Issued | TROY SANDERS |
| Green Building Final | 9/18/2023 | Approved | TROY SANDERS |
| Green Building Rough | 9/18/2023 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 9/18/2023 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 9/18/2023 | Approved | TROY SANDERS |
| Final | 12/20/2023 | OK to Issue CofO | TROY SANDERS |