13817 W ERWIN ST 91401

Certificate Information: 13817 W ERWIN ST 91401

Application / Permit
22016-20000-36765
Plan Check / Job No.
B22VN17850
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (d)
Permit Issued
Issued on 5/12/2023
Issuing Office
Current Status
CofO Issued on 12/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/8/2022 APPLICANT
Assigned to Plan Check Engineer 12/15/2022 JEROME MAGAT PALMA
Corrections Issued 12/16/2022 JEROME MAGAT PALMA
Plan Check Approved 2/1/2023 JEROME MAGAT PALMA
Issued 5/12/2023 APPLICANT
CofO in Progress 10/23/2023 RYAN SALAZAR
Permit Finaled 12/29/2023 RUBEN SALAS
CofO Issued 12/29/2023 RUBEN SALAS
Permit Finaled 12/29/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/20/2022 FERNANDO GIL
Sewer availability Cleared 12/20/2022 FERNANDO GIL
Eng Process Fee Ord 176,300 Cleared 12/21/2022 FERNANDO GIL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/25/2023 No Access for Inspection RYAN SALAZAR
Footing/Foundation/Slab 6/9/2023 Approved RYAN SALAZAR
PLUMBING-Rough 6/9/2023 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 6/26/2023 Not Ready for Inspection RYAN SALAZAR
ELECTRICAL-Rough 6/26/2023 Approved RYAN SALAZAR
Green Building Rough 6/26/2023 Not Ready for Inspection RYAN SALAZAR
HVAC-Rough 6/26/2023 Not Ready for Inspection RYAN SALAZAR
Insulation 6/26/2023 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 6/26/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 7/10/2023 Approved RYAN SALAZAR
Green Building Rough 7/10/2023 Approved RYAN SALAZAR
HVAC-Rough 7/10/2023 Approved RYAN SALAZAR
Insulation 7/10/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 7/10/2023 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 8/7/2023 Approved RYAN SALAZAR
Gas Test 8/7/2023 Approved RYAN SALAZAR
PLUMBING-Rough 8/7/2023 Approved RYAN SALAZAR
Sewer 8/7/2023 Approved RYAN SALAZAR
Wood Frame 8/7/2023 Approved RYAN SALAZAR
Drywall Nailing 8/14/2023 Approved RYAN SALAZAR
Shower Pan 8/14/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 8/25/2023 Approved RYAN SALAZAR
Final 10/13/2023 Corrections Issued RYAN SALAZAR
Green Building Final 10/13/2023 Not Ready for Inspection RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 10/13/2023 SGSOV Approved RYAN SALAZAR
Smoke Detectors 10/13/2023 Approved RYAN SALAZAR
Final 10/20/2023 OK to Issue CofO RYAN SALAZAR
Green Building Final 10/20/2023 Approved RYAN SALAZAR
Service/Power Release 10/20/2023 Approved RYAN SALAZAR