15531-15533 W ROMAR ST 91345

Certificate Information: 15531-15533 W ROMAR ST 91345

Application / Permit
22016-20000-36382
Plan Check / Job No.
B22VN17720
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: CONVERT (E) ATTACHED GARAGE AND PORTION OF (E) S.F.D. INTO A (N) IRREGULAR SHAPED 28'-4" x 20'-2" ATTACHED ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33(c) AND (e) PER WFPP
Permit Issued
Issued on 2/8/2023
Issuing Office
Current Status
CofO Issued on 8/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/1/2022 APPLICANT
Assigned to Plan Check Engineer 12/7/2022 ALFRED RAMIREZ
Corrections Issued 12/8/2022 ALFRED RAMIREZ
Plan Check Approved 2/8/2023 ALFRED RAMIREZ
Issued 2/8/2023 APPLICANT
CofO in Progress 8/1/2024 JENNIFER RABUCHIN
CofO Issued 8/14/2024 DANIEL ORRANTE
Permit Finaled 8/14/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/21/2022 FERNANDO GIL
Sewer availability Cleared 12/21/2022 FERNANDO GIL
Eng Process Fee Ord 176,300 Cleared 1/3/2023 FERNANDO GIL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Test 5/26/2023 No Access for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 5/26/2023 No Access for Inspection JENNIFER RABUCHIN
Gas Test 6/5/2023 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 6/5/2023 Corrections Issued JENNIFER RABUCHIN
Deputy Drilled-In Anchors 6/20/2023 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 6/26/2023 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 6/26/2023 Approved JENNIFER RABUCHIN
PLUMBING-Rough 6/26/2023 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 10/26/2023 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 10/26/2023 Corrections Issued JENNIFER RABUCHIN
MERV13>=Rough 10/26/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/22/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 11/22/2023 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 11/22/2023 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 1/10/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 1/10/2024 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 1/10/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 4/15/2024 Corrections Issued JENNIFER RABUCHIN
Final 4/15/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 4/15/2024 Approved JENNIFER RABUCHIN
MERV13>=Final 4/15/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 4/15/2024 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 4/15/2024 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 4/15/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 4/25/2024 Approved JENNIFER RABUCHIN
Final 4/25/2024 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 4/25/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 4/25/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 4/25/2024 SGSOV Approved JENNIFER RABUCHIN
Final 5/14/2024 Corrections Issued RAUL OLAGI
Final 8/2/2024 OK to Issue CofO JENNIFER RABUCHIN