15531-15533 W ROMAR ST 91345
Certificate Information: 15531-15533 W ROMAR ST 91345
- Application / Permit
- 22016-20000-36382
- Plan Check / Job No.
- B22VN17720
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: CONVERT (E) ATTACHED GARAGE AND PORTION OF (E) S.F.D. INTO A (N) IRREGULAR SHAPED 28'-4" x 20'-2" ATTACHED ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33(c) AND (e) PER WFPP
- Permit Issued
- Issued on 2/8/2023
- Issuing Office
- Current Status
- CofO Issued on 8/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/7/2022 | ALFRED RAMIREZ |
| Corrections Issued | 12/8/2022 | ALFRED RAMIREZ |
| Plan Check Approved | 2/8/2023 | ALFRED RAMIREZ |
| Issued | 2/8/2023 | APPLICANT |
| CofO in Progress | 8/1/2024 | JENNIFER RABUCHIN |
| CofO Issued | 8/14/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/14/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 12/21/2022 | FERNANDO GIL |
| Sewer availability | Cleared | 12/21/2022 | FERNANDO GIL |
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2023 | FERNANDO GIL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Test | 5/26/2023 | No Access for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/26/2023 | No Access for Inspection | JENNIFER RABUCHIN |
| Gas Test | 6/5/2023 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/5/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 6/20/2023 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 6/26/2023 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 6/26/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/26/2023 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/26/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2023 | Corrections Issued | JENNIFER RABUCHIN |
| MERV13>=Rough | 10/26/2023 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/22/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 11/22/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 11/22/2023 | Partial Approval | JENNIFER RABUCHIN |
| Drywall Nailing | 1/10/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 1/10/2024 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 4/15/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 4/15/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 4/15/2024 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 4/15/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 4/15/2024 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 4/15/2024 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 4/15/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 4/25/2024 | Approved | JENNIFER RABUCHIN |
| Final | 4/25/2024 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 4/25/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 4/25/2024 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 4/25/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Final | 5/14/2024 | Corrections Issued | RAUL OLAGI |
| Final | 8/2/2024 | OK to Issue CofO | JENNIFER RABUCHIN |