6656 N SATSUMA AVE 91606

Certificate Information: 6656 N SATSUMA AVE 91606

Application / Permit
22016-20000-36089
Plan Check / Job No.
B22VN17589
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLAN- CONVERT (18x20) DETACHED 2-CAR GARAGE TO 1-BEDROOM ADU (332 SF) PER CA 65852.2(e)(1)(A).
Permit Issued
Issued on 4/25/2023
Issuing Office
Current Status
CofO Issued on 4/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/2/2022 APPLICANT
Assigned to Plan Check Engineer 12/8/2022 VIVIAN LAO
Corrections Issued 12/9/2022 VIVIAN LAO
Plan Check Approved 2/1/2023 JESSE JIMENEZ
Issued 4/25/2023 APPLICANT
CofO in Progress 2/26/2024 JOHN HAYES
Permit Finaled 4/3/2024 RUBEN SALAS
CofO Issued 4/3/2024 RUBEN SALAS
Permit Finaled 4/3/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/29/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 12/29/2022 COLIN LOREDO
Sewer availability Cleared 12/29/2022 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/12/2023 Partial Approval JOHN HAYES
Sewer 7/12/2023 Corrections Issued JOHN HAYES
Underground Mechanical 7/12/2023 Partial Approval JOHN HAYES
PLUMBING-Rough 7/14/2023 Corrections Issued JOHN HAYES
Pre-Inspection 7/14/2023 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 7/20/2023 Partial Approval THOMAS FINNILA
Deputy Drilled-In Anchors 7/24/2023 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 7/27/2023 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 8/4/2023 Approved JOHN HAYES
BUILDING-Rough-Frame 8/21/2023 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 9/25/2023 Corrections Issued JOHN HAYES
Green Building Rough 9/25/2023 Approved JOHN HAYES
BUILDING-Rough-Frame 10/3/2023 Corrections Issued MISAEL ESPARZA
Deputy Wood Construction 10/10/2023 Conditional Approval JOHN HAYES
BUILDING-Rough-Frame 10/12/2023 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 10/18/2023 Partial Approval JOHN HAYES
ELECTRICAL-Rough 10/18/2023 Partial Approval JOHN HAYES
Interior/Exterior Lathing 10/18/2023 Partial Approval JOHN HAYES
PLUMBING-Rough 10/18/2023 Partial Approval JOHN HAYES
Special/Order Compliance 10/18/2023 Corrections Issued JOHN HAYES
Insulation 10/26/2023 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 10/26/2023 Partial Inspection MISAEL ESPARZA
Shower Pan 10/26/2023 Approved MISAEL ESPARZA
Drywall Nailing 11/7/2023 Approved JOHN HAYES
BUILDING-Rough-Frame 1/22/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 1/22/2024 Corrections Issued JENNIFER RABUCHIN
Final 1/22/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 1/22/2024 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 1/22/2024 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 1/22/2024 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 2/12/2024 Approved JENNIFER RABUCHIN
Green Building Final 2/12/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 2/12/2024 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 2/12/2024 Corrections Issued JENNIFER RABUCHIN
Smoke Detectors 2/12/2024 Approved JENNIFER RABUCHIN
Final 2/26/2024 OK to Issue CofO JOHN HAYES