2640 N WESTRIDGE ROAD 90049

Certificate Information: 2640 N WESTRIDGE ROAD 90049

Application / Permit
22016-20000-35989
Plan Check / Job No.
B22VN17529
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
KITCHEN EXTENSION AND RENOVATION, CONVERT PATIO TO EXTENSION OF KITCHEN TO (E) SFD
Permit Issued
Issued on 2/28/2023
Issuing Office
Valley
Current Status
CofO Issued on 11/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/29/2022 APPLICANT
Assigned to Plan Check Engineer 12/22/2022 SELLA BENYAMIN
Corrections Issued 12/29/2022 SELLA BENYAMIN
Quality Review Completed 1/6/2023 STEVEN KIM
Building Plans Picked Up 1/9/2023 APPLICANT
Plan Check Approved 2/28/2023 SELLA BENYAMIN
Issued 2/28/2023 APPLICANT
CofO in Progress 11/9/2023 KEVIN SARGSYAN
Permit Finaled 11/21/2023 DANIEL ORRANTE
CofO Issued 11/21/2023 DANIEL ORRANTE
Permit Finaled 11/21/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/15/2023 CATHERINE ADROVER
Roof/Waste drainage to street Cleared 2/15/2023 CATHERINE ADROVER

Contact Information

Contractor L A Construction And Maintenance; Lic. No.: 1000738-B 9901 LA TUNA CANYON RD      SUN VALLEY, CA 91352
Engineer Bell,, William Andrew; Lic. No.: C88870 550 DEEP VALLEY DR STE 273      ROLLING HILLS ESTATES, CA 90274

Inspector Information

KEVIN SARGSYAN, (310) 914-3889 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/8/2023 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 3/18/2023 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 5/30/2023 Partial Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 5/30/2023 Corrections Issued KEVIN SARGSYAN
FLOOD-Proofing Certificate 5/30/2023 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 5/30/2023 Partial Approval KEVIN SARGSYAN
Deputy Wood Construction 6/1/2023 Conditional Approval KEVIN SARGSYAN
ELECTRICAL-Rough 6/2/2023 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 6/2/2023 Approved KEVIN SARGSYAN
HVAC-Rough 6/5/2023 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 6/5/2023 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 6/6/2023 Approved KEVIN SARGSYAN
PLUMBING-Rough 6/6/2023 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 6/9/2023 Approved KEVIN SARGSYAN
Green Building Rough 6/9/2023 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 6/9/2023 Partial Approval KEVIN SARGSYAN
Insulation 6/13/2023 Approved KENNETH NAGLE
Drywall Nailing 6/21/2023 Approved KENNETH NAGLE
Final 10/12/2023 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 10/12/2023 Approved KEVIN SARGSYAN
Green Building Final 10/12/2023 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 10/12/2023 SGSOV Not Ready KEVIN SARGSYAN
Smoke Detectors 10/12/2023 Not Ready for Inspection KEVIN SARGSYAN
Final 10/30/2023 Corrections Issued ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 10/30/2023 SGSOV Not Ready ARAM AVEDISIAN
Smoke Detectors 10/30/2023 Approved ARAM AVEDISIAN
Final 11/9/2023 OK to Issue CofO KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 11/9/2023 SGSOV Approved KEVIN SARGSYAN