13692 N DE GARMO AVE 91342

Certificate Information: 13692 N DE GARMO AVE 91342

Application / Permit
22016-20000-35691
Plan Check / Job No.
B22VN17447
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan CONVERT DETACHED STORAGE INTO ADU adu checked per ca govt code 65852.2(e)(1)(a)
Permit Issued
Issued on 1/5/2023
Issuing Office
Current Status
CofO Issued on 4/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/27/2022 APPLICANT
Assigned to Plan Check Engineer 12/1/2022 HANS SANTIAGO
Corrections Issued 12/2/2022 SUNMIN LEE
Plan Check Approved 1/3/2023 ANDREW SANTIAGO
Issued 1/5/2023 APPLICANT
CofO in Progress 3/19/2025 KEVIN BERBERYAN
Permit Finaled 4/1/2025 RUBEN SALAS
CofO Issued 4/1/2025 RUBEN SALAS
Permit Finaled 4/1/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/6/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 12/6/2022 CARLOS AGUILERA
Sewer availability Cleared 12/6/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/7/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/24/2023 Conditional Approval MICHAEL SMITH
PLUMBING-Rough 5/25/2023 Approved ARAM AVEDISIAN
Wood Frame 5/25/2023 Partial Approval ARAM AVEDISIAN
Insulation 6/2/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 6/2/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Wood Frame 6/2/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Shower Pan 6/7/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Wood Frame 6/7/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 6/9/2023 Not Ready for Inspection DAVID MATSON
Shower Pan 6/9/2023 Approved DAVID MATSON
Wood Frame 6/9/2023 Not Ready for Inspection DAVID MATSON
ELECTRICAL-Rough 7/12/2023 Corrections Issued RAUL OLAGI
HVAC-Rough 7/12/2023 Corrections Issued RAUL OLAGI
Special/Order Compliance 7/12/2023 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 7/24/2023 Approved MICHEL ABAJAN
ELECTRICAL-Rough 7/24/2023 Approved MICHEL ABAJAN
HVAC-Rough 7/24/2023 Approved MICHEL ABAJAN
MERV13>=Rough 7/24/2023 Approved MICHEL ABAJAN
Insulation 7/27/2023 Not Ready for Inspection RAUL OLAGI
Insulation 8/3/2023 Approved MICHEL ABAJAN
Drywall Nailing 8/17/2023 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 8/17/2023 Corrections Issued KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 4/5/2024 SGSOV Not Ready KEVIN BERBERYAN
Final 5/30/2024 Not Ready for Inspection KEVIN BERBERYAN
MERV13>=Final 5/30/2024 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 5/30/2024 SGSOV Not Ready KEVIN BERBERYAN
Smoke Detectors 5/30/2024 Not Ready for Inspection KEVIN BERBERYAN
Final 10/31/2024 Partial Inspection KEVIN BERBERYAN
MERV13>=Final 10/31/2024 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 10/31/2024 SGSOV Not Ready KEVIN BERBERYAN
Smoke Detectors 10/31/2024 Not Ready for Inspection KEVIN BERBERYAN
Final 2/26/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
MERV13>=Final 2/26/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 2/26/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Smoke Detectors 2/26/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 3/13/2025 Corrections Issued KEVIN BERBERYAN
MERV13>=Final 3/13/2025 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 3/13/2025 SGSOV Not Ready KEVIN BERBERYAN
Smoke Detectors 3/13/2025 Approved KEVIN BERBERYAN
Final 3/19/2025 OK to Issue CofO KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 3/19/2025 SGSOV Approved KEVIN BERBERYAN
Service/Power Release 3/19/2025 Approved KEVIN BERBERYAN