1805 1/2 W 35TH ST 90018

Certificate Information: 1805 1/2 W 35TH ST 90018

Application / Permit
22016-20000-35479
Plan Check / Job No.
B22VN17377
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 2ND FLR RECREATION RM (30'X19') OF EX 2-STORY BLDG W/ GARAGE & BREEZEWAY BELOW INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d).
Permit Issued
Issued on 4/6/2023
Issuing Office
Current Status
CofO Issued on 7/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/23/2022 APPLICANT
Assigned to Plan Check Engineer 11/28/2022 HAYATO TSUCHIYA
Corrections Issued 11/28/2022 HAYATO TSUCHIYA
Building Plans Picked Up 11/29/2022 APPLICANT
Plan Check Approved 4/6/2023 MOHAMMAD ESMAILI
Issued 4/6/2023 APPLICANT
CofO in Progress 7/12/2023 SABAS ALONSO
Permit Finaled 7/30/2023 DEROLD HAUFF
CofO Issued 7/30/2023 DEROLD HAUFF
Permit Finaled 7/30/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/21/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/21/2023 JEANIE LAM
Sewer availability Cleared 3/21/2023 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/18/2023 Partial Inspection SABAS ALONSO
Pre-Inspection 4/25/2023 Partial Inspection SABAS ALONSO
BUILDING-Rough-Frame 6/27/2023 Conditional Approval SABAS ALONSO
ELECTRICAL-Rough 6/27/2023 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 6/27/2023 Approved SABAS ALONSO
Footing/Foundation/Slab 6/27/2023 Approved SABAS ALONSO
Green Building Rough 6/27/2023 Approved SABAS ALONSO
HVAC-Rough 6/27/2023 Approved SABAS ALONSO
Insulation 6/27/2023 Conditional Approval SABAS ALONSO
METHANE-Rough 6/27/2023 Corrections Issued SABAS ALONSO
PLUMBING-Rough 6/27/2023 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 6/27/2023 SGSOV Not Ready SABAS ALONSO
BUILDING-Rough-Frame 7/5/2023 Approved SABAS ALONSO
METHANE-Final 7/5/2023 Approved SABAS ALONSO
METHANE-Rough 7/5/2023 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 7/5/2023 SGSOV Approved SABAS ALONSO
Smoke Detectors 7/5/2023 Approved SABAS ALONSO
Final 7/11/2023 OK to Issue CofO SABAS ALONSO