17642 W TRIBUNE ST 91344
Certificate Information: 17642 W TRIBUNE ST 91344
- Application / Permit
- 22016-20000-35451
- Plan Check / Job No.
- B22VN17350
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (e) det. storage into ADU per GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 3/6/2023
- Issuing Office
- Current Status
- CofO Issued on 1/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/29/2022 | RAMA DABADGE |
| Corrections Issued | 11/30/2022 | RAMA DABADGE |
| Building Plans Picked Up | 12/1/2022 | APPLICANT |
| Applicant returned to address corrections | 3/2/2023 | ALEC MOUSAKHANIAN |
| Issued | 3/6/2023 | APPLICANT |
| CofO in Progress | 1/22/2025 | STEVEN BACK |
| CofO Issued | 1/24/2025 | JOHN JANSON |
| Permit Finaled | 1/24/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/22/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/22/2022 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 12/22/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 12/22/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 12/22/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 12/22/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 12/22/2022 | MEGAN GODINEZ |
| Construction near power lines | Cleared | 1/21/2023 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/28/2023 | Partial Inspection | STEVEN BACK |
| ELECTRICAL-Rough | 9/1/2023 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 9/1/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| PLUMBING-Rough | 9/1/2023 | Corrections Issued | JUSTIN HAWLEY |
| Special/Order Compliance | 9/1/2023 | Corrections Issued | JUSTIN HAWLEY |
| Sewer | 9/6/2023 | Approved | STEVEN BACK |
| HVAC-Rough | 10/17/2023 | Approved | STEVEN BACK |
| PLUMBING-Rough | 10/17/2023 | Approved | STEVEN BACK |
| Underground Mechanical | 10/17/2023 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 10/26/2023 | Approved | STEVEN BACK |
| Green Building Rough | 10/26/2023 | Approved | STEVEN BACK |
| Insulation | 11/7/2023 | Approved | JOHN KIDWELL |
| Drywall Nailing | 11/21/2023 | Partial Approval | HENRY KIM |
| Shower Pan | 11/28/2023 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 12/5/2023 | Approved | MORRIS JACKSON |
| Final | 4/25/2024 | Not Ready for Inspection | STEVEN BACK |
| Gas Test | 4/25/2024 | Not Ready for Inspection | STEVEN BACK |
| Green Building Final | 4/25/2024 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 4/25/2024 | SGSOV Approved | STEVEN BACK |
| Service/Power Release | 4/25/2024 | Not Ready for Inspection | STEVEN BACK |
| Smoke Detectors | 4/25/2024 | Not Ready for Inspection | STEVEN BACK |
| Final | 5/7/2024 | Corrections Issued | STEVEN BACK |
| Gas Test | 5/7/2024 | Approved | STEVEN BACK |
| Service/Power Release | 5/7/2024 | Not Ready for Inspection | STEVEN BACK |
| Smoke Detectors | 5/7/2024 | Approved | STEVEN BACK |
| Final | 5/15/2024 | Corrections Issued | STEVEN BACK |
| Final | 1/17/2025 | Not Ready for Inspection | STEVEN BACK |
| Pre-Inspection | 1/17/2025 | Approved | JUAN ALVARADO |
| Final | 1/22/2025 | OK to Issue CofO | STEVEN BACK |
| Service/Power Release | 1/22/2025 | Approved | STEVEN BACK |