11275-11277 N HERRICK AVE 91331
Certificate Information: 11275-11277 N HERRICK AVE 91331
- Application / Permit
- 22016-20000-35380
- Plan Check / Job No.
- B22VN17348
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Junior Accessory Dwelling Unit
- Work Description
- eplan CONVERT A PORTION OF THE EXISTING HOUSE INTO JADU (499SQFT) PER GCS 65852.2(e)(1)(A) AND 65852.22
- Permit Issued
- Issued on 12/13/2023
- Issuing Office
- Current Status
- CofO Issued on 7/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/7/2022 | JOHNPAUL ISIP |
| Corrections Issued | 12/8/2022 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 12/6/2023 | KHUONG TRUONG |
| Plan Check Approved | 12/12/2023 | JOHNPAUL ISIP |
| Issued | 12/13/2023 | APPLICANT |
| CofO in Progress | 7/15/2024 | MICHEL ABAJAN |
| CofO Issued | 7/23/2024 | RUBEN SALAS |
| Permit Finaled | 7/23/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/12/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/12/2022 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 12/12/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 12/12/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 12/12/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 12/12/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 12/12/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/28/2024 | Corrections Issued | JOHN COLEMAN |
| BUILDING-Rough-Frame | 6/3/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 6/3/2024 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 6/3/2024 | Approved | MICHEL ABAJAN |
| Insulation | 6/3/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| METHANE-Rough | 6/3/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 6/3/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 7/5/2024 | Approved | MICHEL ABAJAN |
| Pre-Inspection | 7/5/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 7/12/2024 | Approved | MICHEL ABAJAN |
| Final | 7/12/2024 | OK to Issue CofO | MICHEL ABAJAN |
| HVAC-Final | 7/12/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 7/12/2024 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/12/2024 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 7/12/2024 | Approved | MICHEL ABAJAN |
| Smoke Detectors | 7/12/2024 | Approved | MICHEL ABAJAN |