5907 W 75TH ST 90045

Certificate Information: 5907 W 75TH ST 90045

Application / Permit
22016-20000-35353
Plan Check / Job No.
B22VN17328
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED INT REMODEL - REMOVE WALLS BETWEEN LIVING RM/DINING RM & KITCHEN TO ENLARGE & CREATE ONE OPEN LIV/DIN/KITCHEN AREA. CONVERT EX KITCHEN INTO BATHRM & PANTRY. RELOCATE KITCHEN. REPLACE TWO EXISTING SLIDING DOOR-NO CHANGE IN SIZE
Permit Issued
Issued on 12/13/2022
Issuing Office
Metro
Current Status
Permit Finaled on 3/3/2023

Permit Application Status History

Submitted 11/22/2022 APPLICANT
Assigned to Plan Check Engineer 11/22/2022 HAYATO TSUCHIYA
Corrections Issued 11/22/2022 HAYATO TSUCHIYA
Building Plans Picked Up 11/29/2022 APPLICANT
Applicant returned to address corrections 12/6/2022 RAMA DABADGE
Issued 12/13/2022 APPLICANT
Permit Finaled 3/2/2023 HERBERT GIRON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/12/2022 VASIL MIHALEV

Contact Information

Contractor Eden Development & Consulting Inc; Lic. No.: 984612-B 13455 VENTURA BLVD STE 215      SHERMAN OAKS, CA 91423
Engineer Mani,, Dev; Lic. No.: C62778 P O BOX 1451      DUARTE, CA 91009

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/16/2022 Approved BOBBY KEY
Interior/Exterior Lathing 12/16/2022 Partial Approval BOBBY KEY
Wood Frame 12/16/2022 Approved BOBBY KEY
Insulation 12/21/2022 Approved BOBBY KEY
Interior/Exterior Lathing 12/21/2022 Approved BOBBY KEY
Drywall Nailing 12/29/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 2/24/2023 Partial Approval HERBERT GIRON
Final 2/24/2023 Corrections Issued HERBERT GIRON
Green Building Rough 2/24/2023 Approved HERBERT GIRON
MERV13>=Final 2/24/2023 Corrections Issued HERBERT GIRON
MERV13>=Rough 2/24/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 2/24/2023 SGSOV Approved HERBERT GIRON
Smoke Detectors 2/24/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 3/2/2023 Approved HERBERT GIRON
Final 3/2/2023 Permit Finaled HERBERT GIRON
MERV13>=Final 3/2/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 3/2/2023 SGSOV Approved HERBERT GIRON
Smoke Detectors 3/2/2023 Approved HERBERT GIRON