7250-7252 N RUBIO AVE 91406

Certificate Information: 7250-7252 N RUBIO AVE 91406

Application / Permit
22016-20000-35241
Plan Check / Job No.
B22VN17284
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan: CONVERT (E) RUMPUS ROOM ON SECOND FLOOR OF (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 1/10/2023
Issuing Office
Current Status
CofO Issued on 5/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/28/2022 APPLICANT
Assigned to Plan Check Engineer 12/1/2022 ALEC MOUSAKHANIAN
Corrections Issued 12/2/2022 ALEC MOUSAKHANIAN
Plan Check Approved 1/9/2023 DANIEL YIP
Issued 1/10/2023 APPLICANT
CofO in Progress 5/11/2023 RAUL OLAGI
Permit Finaled 5/11/2023 MICHAEL SMITH
CofO Issued 5/11/2023 MICHAEL SMITH
Permit Finaled 5/11/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/12/2022 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 12/12/2022 MEGAN GODINEZ
Sewer availability Cleared 12/12/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 1/3/2023 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 1/3/2023 MEGAN GODINEZ
Public Works-Open Permits Cleared 1/3/2023 MEGAN GODINEZ
Public Works-Sewers Cleared 1/3/2023 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 1/30/2023 Approved RAUL OLAGI
Underground Mechanical 1/30/2023 Partial Approval RAUL OLAGI
PLUMBING-Rough 2/16/2023 Approved RAUL OLAGI
ELECTRICAL-Rough 2/17/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 2/24/2023 Corrections Issued RAUL OLAGI
HVAC-Rough 2/24/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 2/24/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 3/20/2023 Corrections Issued RAUL OLAGI
Drywall Nailing 3/20/2023 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 4/5/2023 Approved MATTHEW NELSON
Drywall Nailing 4/5/2023 Approved MATTHEW NELSON
PLUMBING-Final 4/10/2023 Approved RAUL OLAGI
ELECTRICAL-Final 4/14/2023 Approved RAUL OLAGI
Final 5/2/2023 Corrections Issued RAUL OLAGI
HVAC-Final 5/2/2023 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 5/2/2023 SGSOV Approved RAUL OLAGI
Smoke Detectors 5/2/2023 Approved RAUL OLAGI
Final 5/11/2023 OK to Issue CofO RAUL OLAGI