220-220 1/2 E VERNON AVE 4 90011

Certificate Information: 220-220 1/2 E VERNON AVE 4 90011

Application / Permit
22016-20000-35126
Plan Check / Job No.
B22VN17225
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
eplan CONVERTING PART OF THE EXISTING DEWING UNIT TO ADU ADU PER PER LAMC 12.22 A.33(c) AND (e)
Permit Issued
Issued on 1/9/2023
Issuing Office
Current Status
CofO Issued on 3/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/20/2022 APPLICANT
Assigned to Plan Check Engineer 11/22/2022 JAD BASMA
Corrections Issued 11/25/2022 JAD BASMA
Quality Review Completed 12/6/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 12/21/2022 JAD BASMA
Plan Check Approved 12/22/2022 JAD BASMA
Issued 1/9/2023 APPLICANT
CofO in Progress 2/21/2024 MARTIN TAVITIAN
CofO Issued 3/29/2024 ERNESTO CORRAL
Permit Finaled 3/29/2024 ERNESTO CORRAL

Permit Application Clearance Information

Historic Resource Verification Cleared 12/1/2022 MAX LODER
Redevelopment Project Area Cleared 12/5/2022 DAVID URITA
Address approval Cleared 12/6/2022 AMAAN MALIK
Sewer availability Cleared 12/6/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 12/9/2022 AMAAN MALIK

Contact Information

Contractor Elm Construction; Lic. No.: 1018660-B       ,
Engineer Dominguez,, Refugio; Lic. No.: NA50820       ,

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Rough 2/10/2023 Not Ready for Inspection ALAN MORELOS
Wood Frame 2/10/2023 Corrections Issued ALAN MORELOS
Green Building Rough 2/15/2023 Approved ALAN MORELOS
SGSOV-Seismic Gas S/O Valve 2/15/2023 SGSOV Not Ready ALAN MORELOS
Wood Frame 2/15/2023 Corrections Issued ALAN MORELOS
Wood Frame 3/9/2023 Approved ALAN MORELOS
Final 6/1/2023 Not Ready for Inspection ALFREDO LOPEZ
Green Building Final 6/1/2023 Not Ready for Inspection ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 6/1/2023 SGSOV Not Ready ALFREDO LOPEZ
Smoke Detectors 6/1/2023 Not Ready for Inspection ALFREDO LOPEZ
Final 11/16/2023 Not Ready for Inspection MARTIN TAVITIAN
Green Building Final 11/16/2023 Not Ready for Inspection MARTIN TAVITIAN
SGSOV-Seismic Gas S/O Valve 11/16/2023 SGSOV Not Ready MARTIN TAVITIAN
Smoke Detectors 11/16/2023 Not Ready for Inspection MARTIN TAVITIAN
Final 2/16/2024 Not Ready for Inspection MARTIN TAVITIAN
Green Building Final 2/16/2024 Approved MARTIN TAVITIAN
SGSOV-Seismic Gas S/O Valve 2/16/2024 SGSOV Approved MARTIN TAVITIAN
Smoke Detectors 2/16/2024 Approved MARTIN TAVITIAN
Final 2/21/2024 OK to Issue CofO MARTIN TAVITIAN