220-220 1/2 E VERNON AVE 4 90011
Certificate Information: 220-220 1/2 E VERNON AVE 4 90011
- Application / Permit
- 22016-20000-35126
- Plan Check / Job No.
- B22VN17225
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- eplan CONVERTING PART OF THE EXISTING DEWING UNIT TO ADU ADU PER PER LAMC 12.22 A.33(c) AND (e)
- Permit Issued
- Issued on 1/9/2023
- Issuing Office
- Current Status
- CofO Issued on 3/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/22/2022 | JAD BASMA |
| Corrections Issued | 11/25/2022 | JAD BASMA |
| Quality Review Completed | 12/6/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 12/21/2022 | JAD BASMA |
| Plan Check Approved | 12/22/2022 | JAD BASMA |
| Issued | 1/9/2023 | APPLICANT |
| CofO in Progress | 2/21/2024 | MARTIN TAVITIAN |
| CofO Issued | 3/29/2024 | ERNESTO CORRAL |
| Permit Finaled | 3/29/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 12/1/2022 | MAX LODER |
| Redevelopment Project Area | Cleared | 12/5/2022 | DAVID URITA |
| Address approval | Cleared | 12/6/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 12/6/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 12/9/2022 | AMAAN MALIK |
Contact Information
| Contractor | Elm Construction; Lic. No.: 1018660-B | , |
| Engineer | Dominguez,, Refugio; Lic. No.: NA50820 | , |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 2/10/2023 | Not Ready for Inspection | ALAN MORELOS |
| Wood Frame | 2/10/2023 | Corrections Issued | ALAN MORELOS |
| Green Building Rough | 2/15/2023 | Approved | ALAN MORELOS |
| SGSOV-Seismic Gas S/O Valve | 2/15/2023 | SGSOV Not Ready | ALAN MORELOS |
| Wood Frame | 2/15/2023 | Corrections Issued | ALAN MORELOS |
| Wood Frame | 3/9/2023 | Approved | ALAN MORELOS |
| Final | 6/1/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Green Building Final | 6/1/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 6/1/2023 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 6/1/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Final | 11/16/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| Green Building Final | 11/16/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 11/16/2023 | SGSOV Not Ready | MARTIN TAVITIAN |
| Smoke Detectors | 11/16/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| Final | 2/16/2024 | Not Ready for Inspection | MARTIN TAVITIAN |
| Green Building Final | 2/16/2024 | Approved | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 2/16/2024 | SGSOV Approved | MARTIN TAVITIAN |
| Smoke Detectors | 2/16/2024 | Approved | MARTIN TAVITIAN |
| Final | 2/21/2024 | OK to Issue CofO | MARTIN TAVITIAN |