12122 W VANOWEN ST 91605
Certificate Information: 12122 W VANOWEN ST 91605
- Application / Permit
- 22016-20000-35116
- Plan Check / Job No.
- B22VN17219
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Dental Clinic
- Work Description
- CHANGE OF USE FROM (E) RETAIL STORE AND BEAUTY SALON TO DENTAL OFFICE
- Permit Issued
- Issued on 1/24/2023
- Issuing Office
- Current Status
- CofO Issued on 2/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/28/2022 | JEROME MAGAT PALMA |
| Corrections Issued | 11/29/2022 | JEROME MAGAT PALMA |
| Plan Check Approved | 12/27/2022 | SHANGQIN XIE |
| Issued | 1/24/2023 | APPLICANT |
| TCO Issued (Expire Date: 03-03-2024) | 9/5/2023 | JEFFREY DURAN |
| CofO in Progress | 2/8/2024 | ROBERT DAVIS |
| Permit Finaled | 2/8/2024 | JEFFREY DURAN |
| CofO Issued | 2/8/2024 | JEFFREY DURAN |
Permit Application Clearance Information
| Redevelopment Project Area | Cleared | 12/8/2022 | DAVID URITA |
| Eng Process Fee Ord 176,300 | Cleared | 12/14/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 12/14/2022 | DAGOVERTO GUERRERO |
Contact Information
| Architect | Maio,, Miguel J; Lic. No.: C27923 | 13938 ADDISON STREET SHERMAN OAKS, CA 91423 |
| Contractor | J R Development Inc; Lic. No.: 561978-B | , |
| Contractor | Mercury Construction; Lic. No.: 561978-B | , |
| Engineer | Fischer,, Kurt; Lic. No.: S5432 | PO BOX 809 POWAY, CA 92074 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/23/2023 | Approved | ROBERT DAVIS |
| Footing/Foundation/Slab | 3/23/2023 | Approved | ROBERT DAVIS |
| Light Gage Steel Frame | 5/3/2023 | Approved | ROBERT DAVIS |
| Drywall Nailing | 5/11/2023 | Approved | ROBERT DAVIS |
| T-Bar Ceiling | 5/31/2023 | Conditional Approval | ROBERT DAVIS |
| Final | 7/13/2023 | Not Ready for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 7/13/2023 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 7/13/2023 | Not Ready for Inspection | BRIAN KELLY |
| Wood Frame | 7/13/2023 | Not Ready for Inspection | BRIAN KELLY |
| Final | 7/19/2023 | Not Ready for Inspection | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 7/19/2023 | SGSOV No Gas | ROBERT DAVIS |
| Smoke Detectors | 7/19/2023 | Approved | ROBERT DAVIS |
| Wood Frame | 7/19/2023 | Approved | ROBERT DAVIS |
| Final | 8/28/2023 | OK for TCO | ROBERT DAVIS |
| Special/Order Compliance | 2/7/2024 | Not Ready for Inspection | KENNETH ROBERTS |
| Final | 2/8/2024 | OK to Issue CofO | ROBERT DAVIS |